Renewable sites › Ferrybridge Multifuel 2 (FM2)
Ferrybridge Multifuel 2 (FM2)
Ferrybridge Multifuel 2 (FM2) is operational in England with a recorded capacity of 70 MW, and has been generating since 2019-12-20.
Planning and build timeline
| Application submitted | 2014-08-20 |
| Permission granted | 2015-10-28 14 months after submission |
| Operational | 2019-12-20 50 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Ferrybridge Multifuel 1 (FM1) EfW Incineration · Operational | 68 | 0 km |
Kirkhaw Lane Battery · Operational | 20 | 0.4 km |
Kirkhaw Lane - Battery Storage Energy Battery · Operational | 150 | 0.6 km |
Knottingley B Solar Photovoltaics · Operational | 2.4 | 3 km |
Knottingley A Solar Photovoltaics · Operational | 5 | 3 km |
Monk Fryston Battery Storage Battery · Under Construction | 320 | 4.2 km |
Monk Fryston Battery Storage Battery · Under Construction | 57 | 4.4 km |
Sudforth Lane (Kellingley Solar Farm) Solar Photovoltaics · Operational | 5 | 5.6 km |
How big is Ferrybridge Multifuel 2 (FM2)?
Ferrybridge Multifuel 2 (FM2) has a recorded installed capacity of 70 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Ferrybridge Multifuel 2 (FM2)?
REPD records the operator as Scottish and Southern Energy (SSE). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Ferrybridge Multifuel 2 (FM2) approved and built?
The application was submitted on 2014-08-20. Permission was granted on 2015-10-28, 14 months later. The site became operational on 2019-12-20, 50 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3.
Novarly Parcel · official public data, read properly · parcel.novarly.com