Renewable sitesKentish Flats 2

Kentish Flats 2

Kentish Flats 2 is an operational 49.5 MW offshore wind farm in England, generating since 14 September 2015. Planning permission was granted on 19 February 2013, 9 months after submission. Operator of record: Vattenfall.

49.5 MW
Capacity
as recorded in REPD
Operational
Status
since 14 September 2015
Wind Offshore
Technology
Vattenfall
National
Authority
England

Planning and build timeline

Application submitted1 June 2012
Permission granted19 February 2013
9 months after submission
Operational14 September 2015
31 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the same record on your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Kentish Flats 2’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Wind Offshore · Operational
901.5 km
Solar Photovoltaics · Operational
1810.4 km
Solar Photovoltaics · Operational
4811 km
Solar Photovoltaics · Operational
1014.2 km

How big is Kentish Flats 2?

Kentish Flats 2 has a recorded installed capacity of 49.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Kentish Flats 2?

REPD records the operator as Vattenfall. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Kentish Flats 2 approved and built?

The application was submitted on 1 June 2012. Permission was granted on 19 February 2013, 9 months later. The site became operational on 14 September 2015, 31 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2504.