Kentish Flats�

Kentish Flats� is an operational 90 MW offshore wind farm in DECC (S36), generating since 10 September 2005. Planning permission was granted on 1 March 2003, 7 months after submission. Operator of record: Vattenfall.

90 MW
Capacity
as recorded in REPD
Operational
Status
since 10 September 2005
Wind Offshore
Technology
Vattenfall
DECC (S36)
Authority
England

Planning and build timeline

Application submitted15 August 2002
Permission granted1 March 2003
7 months after submission
Operational10 September 2005
30 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in DECC (S36): the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Kentish Flats�’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Wind Offshore · Operational
49.51.5 km
Solar Photovoltaics · Operational
1811.6 km
Solar Photovoltaics · Operational
4812.1 km

How big is Kentish Flats�?

Kentish Flats� has a recorded installed capacity of 90 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Kentish Flats�?

REPD records the operator as Vattenfall. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Kentish Flats� approved and built?

The application was submitted on 15 August 2002. Permission was granted on 1 March 2003, 7 months later. The site became operational on 10 September 2005, 30 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2492.