Renewable sitesTiln Farm solar park

Tiln Farm solar park

Tiln Farm solar park is operational in Bassetlaw with a recorded capacity of 8 MW, and has been generating since 2015-03-31.

8 MW
Capacity
as recorded in REPD
Operational
Status
since 2015-03-31
Solar Photovoltaics
Technology
Pfalz Solar
Bassetlaw
Authority
England

Planning and build timeline

Application submitted2013-09-27
Permission granted2013-12-20
3 months after submission
Operational2015-03-31
15 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Bassetlaw’s record on solar

Bassetlaw has decided 23 solar farms and approved 100%, taking a median of 3 months. See every solar farm decision in Bassetlaw

Other built sites within 15 km

SiteMWDistance
Tiln Farm Retford (extension)
Solar Photovoltaics · Operational
1.70.2 km
Tiln Farm Solar Farm
Solar Photovoltaics · Under Construction
49.90.9 km
Sutton Grange AD Plant
Anaerobic Digestion · Operational
32.7 km
Barnby Moor
Solar Photovoltaics · Operational
44.5 km
Walmoor Farm solar park
Solar Photovoltaics · Operational
45 km
Walkers Wood Solar Park
Solar Photovoltaics · Operational
276 km
Little Morton Solar Farm
Solar Photovoltaics · Operational
14.36.4 km
Jubilee Farm, Barnby Moor
Solar Photovoltaics · Operational
57.2 km

How big is Tiln Farm solar park?

Tiln Farm solar park has a recorded installed capacity of 8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Tiln Farm solar park?

REPD records the operator as Pfalz Solar. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Tiln Farm solar park approved and built?

The application was submitted on 2013-09-27. Permission was granted on 2013-12-20, 3 months later. The site became operational on 2015-03-31, 15 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2356.