Tiln Farm solar park is an operational 8 MW solar farm in Bassetlaw, generating since 31 March 2015. Planning permission was granted on 20 December 2013, 3 months after submission. Operator of record: Pfalz Solar.

8 MW
Capacity
as recorded in REPD
Operational
Status
since 31 March 2015
Solar Photovoltaics
Technology
Pfalz Solar
Bassetlaw
Authority
England

Planning and build timeline

Application submitted27 September 2013
Permission granted20 December 2013
3 months after submission
Operational31 March 2015
15 months after consent

Screening a site of your own?

RedlineUK · £39

Bassetlaw approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Tiln Farm solar park’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Bassetlaw’s record on solar

Bassetlaw has decided 23 solar farms and approved 100%, taking a median of 3 months. See every solar farm decision in Bassetlaw

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
1.70.2 km
Solar Photovoltaics · Under Construction
49.90.9 km
Anaerobic Digestion · Operational
32.7 km
Solar Photovoltaics · Operational
44.5 km
Solar Photovoltaics · Operational
45 km
Solar Photovoltaics · Operational
276 km
Solar Photovoltaics · Operational
14.36.4 km
Solar Photovoltaics · Operational
57.2 km

How big is Tiln Farm solar park?

Tiln Farm solar park has a recorded installed capacity of 8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Tiln Farm solar park?

REPD records the operator as Pfalz Solar. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Tiln Farm solar park approved and built?

The application was submitted on 27 September 2013. Permission was granted on 20 December 2013, 3 months later. The site became operational on 31 March 2015, 15 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2356.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode