Solar planning in Antrim and Newtownabbey

Antrim and Newtownabbey has decided 12 solar farms and approved 83% of them, taking a median of 6.5 months to decide. Consented capacity: 115 MW. 4 applications still awaiting a decision.

83%
Approved
10 granted · 2 refused
6.5 mo
Median decision
UK 2.3 mo
115 MW
Consented
10 MW refused
3
Appeals
1 allowed on appeal

How Antrim and Newtownabbey compares

Against the 298 UK authorities with 5+ solar decisions, Antrim and Newtownabbey sits in the 12th percentile for approval rate (10 points below the England average) and the 2nd percentile for speed.

Decisions by year

35Approved — 4 (2014)414Approved — 2 (2015)Refused — 1 (2015)315Approved — 3 (2016)Refused — 1 (2016)416Approved — 1 (2018)118
Approved Refused

Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (18)

SchemeMWStatusDecided
Solar PV Farm Development in Carrickfergus
Irish Salt Mining & Exploration Co. Limited · LA02/2024/0651/F
Application Submitted2024-09-28
Solar Farm Development in Antrim
Elgin Energy Esco Limited · LA03/2024/0661/S54
20Application Submitted2024-09-04
Dunore Road, Aldergrove Solar Farm
NI Water · LA03/2021/0252/F
3.75Application Submitted2021-03-03
Steeple Road
Elgin Energy Esco · LA03/2016/0135/F · 27.4 mo to decide
25Awaiting Construction2018-05-24
Gibson Farm
Lightsource Renewable Energy · LA03/2015/0655/F · 7.7 mo to decide
6.4Operational2016-07-26
Land north of 20 Knockcairn Road
Lightsource Renewable Energy · LA03/2015/0021/F · 13.8 mo to decide
4.1Application Refused2016-05-23
South Antrim Solar Park - Phase 1
Hadstone Energy · LA03/2015/0262/F · 9.9 mo to decide
6.5Operational2016-04-26
South Antrim Solar Park - Phase 2
Hadstone Energy · LA03/2015/0262/F · 9.9 mo to decide
39.5Awaiting Construction2016-04-25
Lands West of Belfast Road
Lightsource Renewable Energy · LA03/2015/0257/F · 5.8 mo to decide
10Operational2015-12-23
Sealstown Road Solar Farm
Lightsource Renewable Energy · LA03/2015/0250/F · 4.8 mo to decide
6.7Abandoned2015-11-17
Doagh Road Solar Farm
Power Capital · LA03/2015/0025/F · 6.8 mo to decide
5Appeal Withdrawn2015-10-22
South of Ballysculty
Lightsource Renewable Energy · T/2014/0460/F · 9.7 mo to decide
6.2Appeal Refused2015-08-27
Millar Farm
Lightsource Renewable Energy · T/2015/0094/F · 4.6 mo to decide
6Operational2015-07-22
Kells Solar Farm
Elgin Energy EsCo · LA03/2015/0234/F
50Application Submitted2015-06-26
Moira Road
Lightsource Renewable Energy · T/2014/0201/F · 6.2 mo to decide
6.5Operational2014-12-03
Crookedstone Road
Lightsource Renewable Energy · T/2014/0098/F · 5.5 mo to decide
4.8Operational2014-09-08
Knockcairn Road
Lightsource Renewable Energy · T/2014/0066/F · 3.9 mo to decide
6.5Operational2014-06-26
Bombardier Factory
Bombardier Aerospace · Z/2013/1267/F · 3.2 mo to decide
3.8Operational2014-02-07

Does Antrim and Newtownabbey approve solar farms?

Yes — of the 12 solar farms Antrim and Newtownabbey has decided, 83% were approved (10 granted, 2 refused). The UK-wide rate for solar is 93%.

How long does a solar farm application take in Antrim and Newtownabbey?

The median time from application to decision is 6.5 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much solar capacity has Antrim and Newtownabbey consented?

115 MW has been consented across 10 approved schemes, with 10 MW refused. A further 4 applications awaits a decision.

Other technologies in Antrim and Newtownabbey

Battery storage in Antrim and NewtownabbeyOnshore wind in Antrim and Newtownabbey

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.