Renewable sites › Seegronan
Seegronan
Seegronan is operational in Antrim and Newtownabbey with a recorded capacity of 13.8 MW, and has been generating since 2016-08-15.
Planning and build timeline
| Application submitted | 2006-08-24 |
| Permission granted | 2011-01-13 53 months after submission |
| Operational | 2016-08-15 67 months after consent |
Antrim and Newtownabbey’s record on onshore wind
Antrim and Newtownabbey has decided 19 onshore wind schemes and approved 79%, taking a median of 20.4 months. See every onshore wind scheme decision in Antrim and Newtownabbey →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Moira Road Solar Photovoltaics · Operational | 6.5 | 7.7 km |
Crookedstone Road Solar Photovoltaics · Operational | 4.8 | 7.8 km |
South Antrim Solar Park - Phase 1 Solar Photovoltaics · Operational | 6.5 | 8 km |
Knockcairn Road Solar Photovoltaics · Operational | 6.5 | 9 km |
Land to the South of 15 Lough Road Solar Photovoltaics · Operational | 4.8 | 10.9 km |
Hillside Solar Farm Solar Photovoltaics · Operational | 25.2 | 11.2 km |
Lands West of Belfast Road Solar Photovoltaics · Operational | 10 | 12 km |
Millar Farm Solar Photovoltaics · Operational | 6 | 12.7 km |
How big is Seegronan?
Seegronan has a recorded installed capacity of 13.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Seegronan?
REPD records the operator as Seegronan Windfarm. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Seegronan approved and built?
The application was submitted on 2006-08-24. Permission was granted on 2011-01-13, 53 months later. The site became operational on 2016-08-15, 67 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4108.