Middle Muir Wind Farm

Middle Muir Wind Farm is an operational 51 MW onshore wind farm in Scotland, generating since 16 May 2019. Planning permission was granted on 26 September 2014, 32 months after submission. Operator of record: Banks Renewables.

51 MW
Capacity
as recorded in REPD
Operational
Status
since 16 May 2019
Wind Onshore
Technology
Banks Renewables
National
Authority
Scotland

Planning and build timeline

Application submitted7 February 2012
Permission granted26 September 2014
32 months after submission
Operational16 May 2019
56 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the same record on your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Middle Muir Wind Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Scottish Government (S36)’s record on onshore wind

Scottish Government (S36) has decided 173 onshore wind schemes and approved 80%, taking a median of 33.7 months. See every onshore wind scheme decision in Scottish Government (S36)

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
362.7 km
Wind Onshore · Under Construction
1.67.1 km
Wind Onshore · Operational
7.88.7 km
Wind Onshore · Operational
7.88.7 km
Wind Onshore · Under Construction
629.1 km
Wind Onshore · Operational
269.5 km
Wind Onshore · Under Construction
46.29.7 km
Wind Onshore · Operational
459.9 km

How big is Middle Muir Wind Farm?

Middle Muir Wind Farm has a recorded installed capacity of 51 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Middle Muir Wind Farm?

REPD records the operator as Banks Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Middle Muir Wind Farm approved and built?

The application was submitted on 7 February 2012. Permission was granted on 26 September 2014, 32 months later. The site became operational on 16 May 2019, 56 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4440.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode