Renewable sites › Andershaw
Andershaw
Andershaw is operational in South Lanarkshire with a recorded capacity of 36 MW, and has been generating since 2016-11-02.
Planning and build timeline
| Application submitted | 2007-07-09 |
| Permission granted | 2014-06-09 83 months after submission |
| Operational | 2016-11-02 29 months after consent |
South Lanarkshire’s record on onshore wind
South Lanarkshire has decided 49 onshore wind schemes and approved 73%, taking a median of 15.9 months. See every onshore wind scheme decision in South Lanarkshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Middle Muir Wind Farm Wind Onshore · Operational | 51 | 2.7 km |
Hazelside farm Wind Onshore · Under Construction | 1.6 | 5.9 km |
Kennoxhead Wind Farm Wind Onshore · Under Construction | 62 | 6.4 km |
Hagshaw Hill Wind Farm Wind Onshore · Operational | 7.8 | 6.9 km |
Hagshaw Hill Wind Farm Wind Onshore · Operational | 7.8 | 6.9 km |
Hagshaw Hill Wind Farm Extension Wind Onshore · Operational | 26 | 7.9 km |
Galawhistle Wind Onshore · Operational | 66 | 8.8 km |
Douglas West and Dalquhandy Renewable Energy Project Wind Onshore · Operational | 45 | 9.1 km |
How big is Andershaw?
Andershaw has a recorded installed capacity of 36 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Andershaw?
REPD records the operator as Statkraft UK. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Andershaw approved and built?
The application was submitted on 2007-07-09. Permission was granted on 2014-06-09, 83 months later. The site became operational on 2016-11-02, 29 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4110.
Novarly Parcel · official public data, read properly · parcel.novarly.com