Renewable sitesAndershaw

Andershaw

Andershaw is an operational 36 MW onshore wind farm in South Lanarkshire, generating since 2 November 2016. Planning permission was granted on 9 June 2014, 83 months after submission. Operator of record: Statkraft UK.

36 MW
Capacity
as recorded in REPD
Operational
Status
since 2 November 2016
Wind Onshore
Technology
Statkraft UK
South Lanarkshire
Authority
Scotland

Planning and build timeline

Application submitted9 July 2007
Permission granted9 June 2014
83 months after submission
Operational2 November 2016
29 months after consent

Screening a site of your own?

RedlineUK · £39

South Lanarkshire approves 73% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Andershaw’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

South Lanarkshire’s record on onshore wind

South Lanarkshire has decided 49 onshore wind schemes and approved 73%, taking a median of 15.9 months. See every onshore wind scheme decision in South Lanarkshire

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
512.7 km
Wind Onshore · Under Construction
1.65.9 km
Wind Onshore · Under Construction
626.4 km
Wind Onshore · Operational
7.86.9 km
Wind Onshore · Operational
7.86.9 km
Wind Onshore · Operational
267.9 km
Wind Onshore · Operational
668.8 km
Wind Onshore · Operational
459.1 km

How big is Andershaw?

Andershaw has a recorded installed capacity of 36 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Andershaw?

REPD records the operator as Statkraft UK. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Andershaw approved and built?

The application was submitted on 9 July 2007. Permission was granted on 9 June 2014, 83 months later. The site became operational on 2 November 2016, 29 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4110.