Priestgill Wind Farm
Priestgill Wind Farm is under construction in South Lanarkshire with a recorded capacity of 46.2 MW.
Planning and build timeline
| Application submitted | 2016-12-13 |
| Permission granted | 2021-12-15 60 months after submission |
| Operational | not recorded |
South Lanarkshire’s record on onshore wind
South Lanarkshire has decided 49 onshore wind schemes and approved 73%, taking a median of 15.9 months. See every onshore wind scheme decision in South Lanarkshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Clyde Wind Farm Extension (Clyde 2) Wind Onshore · Operational | 172.8 | 6.5 km |
Middle Muir Wind Farm Wind Onshore · Operational | 51 | 9.7 km |
Clyde Wind Farm Wind Onshore · Operational | 350 | 10.3 km |
Whitelaw Brae Wind Farm Wind Onshore · Under Construction | 57 | 10.9 km |
Andershaw Wind Onshore · Operational | 36 | 12.4 km |
Broken Cross (Former Surface Mine) Wind Onshore · Operational | 48 | 14.7 km |
Glenkerie Wind Farm Wind Onshore · Operational | 22 | 14.9 km |
How big is Priestgill Wind Farm?
Priestgill Wind Farm has a recorded installed capacity of 46.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Priestgill Wind Farm?
REPD records the operator as Muirhall Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Priestgill Wind Farm approved and built?
The application was submitted on 2016-12-13. Permission was granted on 2021-12-15, 60 months later. The site is recorded as under construction and has no operational date yet.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6363.