Hazelside farm is a 1.6 MW onshore wind farm under construction in South Lanarkshire. Planning permission was granted on 18 December 2014, 9 months after submission. Operator of record: Mitchell Farming Partnerships (3R Energy).

1.6 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Wind Onshore
Technology
Mitchell Farming Partnerships (3R Energy)
South Lanarkshire
Authority
Scotland

Planning and build timeline

Application submitted1 April 2014
Permission granted18 December 2014
9 months after submission
Operationalnot recorded

Screening a site of your own?

RedlineUK · £39

South Lanarkshire approves 73% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Hazelside farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

South Lanarkshire’s record on onshore wind

South Lanarkshire has decided 49 onshore wind schemes and approved 73%, taking a median of 15.9 months. See every onshore wind scheme decision in South Lanarkshire

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
7.82.3 km
Wind Onshore · Operational
7.82.3 km
Wind Onshore · Operational
262.5 km
Battery · Under Construction
203.3 km
Wind Onshore · Operational
453.3 km
Wind Onshore · Under Construction
783.3 km
Wind Onshore · Under Construction
1264.6 km
Battery · Under Construction
404.6 km

How big is Hazelside farm?

Hazelside farm has a recorded installed capacity of 1.6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Hazelside farm?

REPD records the operator as Mitchell Farming Partnerships (3R Energy). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Hazelside farm approved and built?

The application was submitted on 1 April 2014. Permission was granted on 18 December 2014, 9 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3633.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode