Novarly ParcelRenewable sites

Renewable sitesMeikle Carewe

Meikle Carewe

Meikle Carewe is an operational 10 MW onshore wind farm in Aberdeenshire, generating since 30 July 2013. Planning permission was granted on 20 May 2010, 42 months after submission. Operator of record: The Renewables Infrastructure Group (TRIG).

10 MW
Capacity
as recorded in REPD
Operational
Status
since 30 July 2013
Wind Onshore
Technology
The Renewables Infrastructure Group (TRIG)
Aberdeenshire
Authority
Scotland

Planning and build timeline

Application submitted29 November 2006
Permission granted20 May 2010
42 months after submission
Operational30 July 2013
38 months after consent

Screening a site of your own?

RedlineUK · £39

Aberdeenshire approves 69% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Meikle Carewe’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Aberdeenshire’s record on onshore wind

Aberdeenshire has decided 118 onshore wind schemes and approved 69%, taking a median of 12.7 months. See every onshore wind scheme decision in Aberdeenshire

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
17.57.4 km
Wind Onshore · Operational
5.29.5 km
Wind Onshore · Operational
6.811 km
Wind Onshore · Operational
4.613 km
Biomass (dedicated) · Operational
1.213.3 km
Wind Onshore · Operational
57.513.8 km
Wind Onshore · Operational
18.413.8 km
Wind Onshore · Operational
7.714 km

How big is Meikle Carewe?

Meikle Carewe has a recorded installed capacity of 10 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Meikle Carewe?

REPD records the operator as The Renewables Infrastructure Group (TRIG). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Meikle Carewe approved and built?

The application was submitted on 29 November 2006. Permission was granted on 20 May 2010, 42 months later. The site became operational on 30 July 2013, 38 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4109.