Renewable sites › Mid Hill - Phase II
Mid Hill - Phase II
Mid Hill - Phase II is an operational 18.4 MW onshore wind farm in Scotland, generating since 2 December 2014. Planning permission was granted on 3 June 2005, 28 months after submission. Operator of record: Fred Olsen Renewables.
Planning and build timeline
| Application submitted | 12 February 2003 |
| Permission granted | 3 June 2005 28 months after submission |
| Operational | 2 December 2014 114 months after consent |
Screening a site of your own?
Redline runs the same record on your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Mid Hill - Phase II’s recorded coordinate — swap in your own postcode or coordinates.
Scottish Government (S36)’s record on onshore wind
Scottish Government (S36) has decided 173 onshore wind schemes and approved 80%, taking a median of 33.7 months. See every onshore wind scheme decision in Scottish Government (S36) →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 57.5 | 0 km |
Wind Onshore · Operational | 6.8 | 6.9 km |
Wind Onshore · Operational | 4.6 | 7.3 km |
Biomass (dedicated) · Operational | 1.2 | 8.5 km |
Wind Onshore · Under Construction | 1 | 10.1 km |
Wind Onshore · Operational | 5.2 | 12.5 km |
Wind Onshore · Operational | 10 | 13.8 km |
Wind Onshore · Operational | 7.5 | 14.6 km |
How big is Mid Hill - Phase II?
Mid Hill - Phase II has a recorded installed capacity of 18.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Mid Hill - Phase II?
REPD records the operator as Fred Olsen Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Mid Hill - Phase II approved and built?
The application was submitted on 12 February 2003. Permission was granted on 3 June 2005, 28 months later. The site became operational on 2 December 2014, 114 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4627.