Jacksbank Wind Farm (Glenbervie)
Jacksbank Wind Farm (Glenbervie) is operational in Aberdeenshire with a recorded capacity of 6.8 MW, and has been generating since 2014-07-12.
Planning and build timeline
| Application submitted | 2010-02-22 |
| Permission granted | 2013-04-26 38 months after submission |
| Operational | 2014-07-12 15 months after consent |
Aberdeenshire’s record on onshore wind
Aberdeenshire has decided 118 onshore wind schemes and approved 69%, taking a median of 12.7 months. See every onshore wind scheme decision in Aberdeenshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Droop Hill Wind Farm x Wind Onshore · Operational | 4.6 | 2.1 km |
Macphie of Glenbervie Biomass (dedicated) · Operational | 1.2 | 2.7 km |
Clochnahill Wind Farm Wind Onshore · Operational | 5.2 | 5.9 km |
Mid Hill I Wind Onshore · Operational | 57.5 | 6.9 km |
Mid Hill - Phase II Wind Onshore · Operational | 18.4 | 6.9 km |
St John Hill Wind Onshore · Operational | 7.7 | 8.7 km |
St. Johns Hill Wind Onshore · Operational | 7.65 | 9 km |
Tullo Wind Farm North Extension (Shiels Wind Farm) Wind Onshore · Operational | 7.5 | 10.8 km |
How big is Jacksbank Wind Farm (Glenbervie)?
Jacksbank Wind Farm (Glenbervie) has a recorded installed capacity of 6.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Jacksbank Wind Farm (Glenbervie)?
REPD records the operator as East Coast Viners. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Jacksbank Wind Farm (Glenbervie) approved and built?
The application was submitted on 2010-02-22. Permission was granted on 2013-04-26, 38 months later. The site became operational on 2014-07-12, 15 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4511.