Renewable sites › Tullo Farm
Tullo Farm
Tullo Farm is an operational 17.5 MW onshore wind farm in Aberdeenshire, generating since 7 September 2010. Planning permission was granted on 30 June 2004, 9 months after submission. Operator of record: West Coast Energy (agents for Tullo Wind Ltd and GE Wind).
Planning and build timeline
| Application submitted | 13 October 2003 |
| Permission granted | 30 June 2004 9 months after submission |
| Operational | 7 September 2010 74 months after consent |
Screening a site of your own?
Aberdeenshire approves 69% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Tullo Farm’s recorded coordinate — swap in your own postcode or coordinates.
Aberdeenshire’s record on onshore wind
Aberdeenshire has decided 118 onshore wind schemes and approved 69%, taking a median of 12.7 months. See every onshore wind scheme decision in Aberdeenshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 5.2 | 5.9 km |
Wind Onshore · Operational | 10 | 7.4 km |
Wind Onshore · Operational | 7.7 | 8.7 km |
Wind Onshore · Operational | 7.65 | 9.2 km |
Wind Onshore · Operational | 6.8 | 11 km |
Biomass (dedicated) · Operational | 1.2 | 12.1 km |
Wind Onshore · Operational | 4.6 | 12.4 km |
How big is Tullo Farm?
Tullo Farm has a recorded installed capacity of 17.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Tullo Farm?
REPD records the operator as West Coast Energy (agents for Tullo Wind Ltd and GE Wind). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Tullo Farm approved and built?
The application was submitted on 13 October 2003. Permission was granted on 30 June 2004, 9 months later. The site became operational on 7 September 2010, 74 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3190.