Renewable sites › Mid Hill I
Mid Hill I
Mid Hill I is operational in Scottish Government (S36) with a recorded capacity of 57.5 MW, and has been generating since 2013-12-01.
Planning and build timeline
| Application submitted | 2003-02-12 |
| Permission granted | 2005-06-03 28 months after submission |
| Operational | 2013-12-01 102 months after consent |
Scottish Government (S36)’s record on onshore wind
Scottish Government (S36) has decided 173 onshore wind schemes and approved 80%, taking a median of 33.7 months. See every onshore wind scheme decision in Scottish Government (S36) →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Mid Hill - Phase II Wind Onshore · Operational | 18.4 | 0 km |
Jacksbank Wind Farm (Glenbervie) Wind Onshore · Operational | 6.8 | 6.9 km |
Droop Hill Wind Farm x Wind Onshore · Operational | 4.6 | 7.3 km |
Macphie of Glenbervie Biomass (dedicated) · Operational | 1.2 | 8.5 km |
HydroGlen Project - Glensaugh Farm Wind Onshore · Under Construction | 1 | 10.1 km |
Clochnahill Wind Farm Wind Onshore · Operational | 5.2 | 12.5 km |
Meikle Carewe Wind Onshore · Operational | 10 | 13.8 km |
Tullo Wind Farm North Extension (Shiels Wind Farm) Wind Onshore · Operational | 7.5 | 14.6 km |
How big is Mid Hill I?
Mid Hill I has a recorded installed capacity of 57.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Mid Hill I?
REPD records the operator as Fred Olsen Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Mid Hill I approved and built?
The application was submitted on 2003-02-12. Permission was granted on 2005-06-03, 28 months later. The site became operational on 2013-12-01, 102 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4667.