Novarly ParcelRenewable sites

Renewable sitesMeece Landfill

Meece Landfill

Meece Landfill is operational in Stafford with a recorded capacity of 1.3 MW, and has been generating since 1999-02-24.

1.3 MW
Capacity
as recorded in REPD
Operational
Status
since 1999-02-24
Landfill Gas
Technology
Thomas Graveson Ltd
Stafford
Authority
England

Planning and build timeline

Application submitted1996-04-01
Permission granted1997-03-24
12 months after submission
Operational1999-02-24
23 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Eccleshall Biomass
Biomass (dedicated) · Operational
2.63.6 km
Screwfix Direct
Solar Photovoltaics · Operational
2.58.7 km
Stoke-on-Trent EfW
EfW Incineration · Operational
14.29.9 km
Keele University
Battery · Operational
10.8 km
Keele University
Solar Photovoltaics · Operational
4.410.8 km
The Low Carbon Energy Generation Project at Keele University
Wind Onshore · Operational
1.911.6 km
Stafford Leisure Centre, Lammascote Road - Solar Panels
Solar Photovoltaics · Under Construction
0.2613.1 km
Brookfield Farm AD Plant (Farm AD)
Anaerobic Digestion · Operational
1.314.2 km

How big is Meece Landfill?

Meece Landfill has a recorded installed capacity of 1.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Meece Landfill?

REPD records the operator as Thomas Graveson Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Meece Landfill approved and built?

The application was submitted on 1996-04-01. Permission was granted on 1997-03-24, 12 months later. The site became operational on 1999-02-24, 23 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 561.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council