Eccleshall Biomass

Eccleshall Biomass is operational in Stafford with a recorded capacity of 2.6 MW, and has been generating since 2007-09-12.

2.6 MW
Capacity
as recorded in REPD
Operational
Status
since 2007-09-12
Biomass (dedicated)
Technology
Eccleshal Biomass
Stafford
Authority
England

Planning and build timeline

Application submitted2003-08-05
Permission granted2003-10-29
3 months after submission
Operational2007-09-12
46 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Meece Landfill
Landfill Gas · Operational
1.33.6 km
Brookfield Farm AD Plant (Farm AD)
Anaerobic Digestion · Operational
1.311.1 km
Stafford Leisure Centre, Lammascote Road - Solar Panels
Solar Photovoltaics · Under Construction
0.2612.1 km
Screwfix Direct
Solar Photovoltaics · Operational
2.512.3 km
Stoke-on-Trent EfW
EfW Incineration · Operational
14.213.4 km
Keele University
Solar Photovoltaics · Operational
4.413.5 km
Keele University
Battery · Operational
13.5 km
The Low Carbon Energy Generation Project at Keele University
Wind Onshore · Operational
1.914.3 km

How big is Eccleshall Biomass?

Eccleshall Biomass has a recorded installed capacity of 2.6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Eccleshall Biomass?

REPD records the operator as Eccleshal Biomass. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Eccleshall Biomass approved and built?

The application was submitted on 2003-08-05. Permission was granted on 2003-10-29, 3 months later. The site became operational on 2007-09-12, 46 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 58.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council