Novarly ParcelRenewable sites

Renewable sitesKeele University

Keele University

Keele University is operational in Newcastle-under-Lyme with a recorded capacity of 4.4 MW, and has been generating since 2022-04-29.

4.4 MW
Capacity
as recorded in REPD
Operational
Status
since 2022-04-29
Solar Photovoltaics
Technology
Keele University
Newcastle-under-Lyme
Authority
England

Planning and build timeline

Application submitted2018-12-20
Permission granted2019-02-20
2 months after submission
Operational2022-04-29
38 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Newcastle-under-Lyme’s record on solar

Newcastle-under-Lyme has decided 8 solar farms and approved 100%, taking a median of 1.8 months. See every solar farm decision in Newcastle-under-Lyme

Other built sites within 15 km

SiteMWDistance
Keele University
Battery · Operational
0 km
The Low Carbon Energy Generation Project at Keele University
Wind Onshore · Operational
1.91.1 km
Noriker Power Staunch
Battery · Operational
204.2 km
Stoke-on-Trent EfW
EfW Incineration · Operational
14.25.1 km
Screwfix Direct
Solar Photovoltaics · Operational
2.56.3 km
Meece Landfill
Landfill Gas · Operational
1.310.8 km
Land at Heywood Grange
Solar Photovoltaics · Operational
8.413.3 km
Eccleshall Biomass
Biomass (dedicated) · Operational
2.613.5 km

How big is Keele University?

Keele University has a recorded installed capacity of 4.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Keele University?

REPD records the operator as Keele University. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Keele University approved and built?

The application was submitted on 2018-12-20. Permission was granted on 2019-02-20, 2 months later. The site became operational on 2022-04-29, 38 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7409.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council