Renewable sites › Screwfix Direct
Screwfix Direct
Screwfix Direct is operational in Stoke-on-Trent with a recorded capacity of 2.5 MW, and has been generating since 2016-01-12.
Planning and build timeline
| Application submitted | 2015-10-08 |
| Permission granted | 2015-11-03 1 months after submission |
| Operational | 2016-01-12 2 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Stoke-on-Trent’s record on solar
Stoke-on-Trent has decided 19 solar farms and approved 95%, taking a median of 1.7 months. See every solar farm decision in Stoke-on-Trent →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Stoke-on-Trent EfW EfW Incineration · Operational | 14.2 | 1.7 km |
Keele University Battery · Operational | — | 6.3 km |
Keele University Solar Photovoltaics · Operational | 4.4 | 6.3 km |
The Low Carbon Energy Generation Project at Keele University Wind Onshore · Operational | 1.9 | 7.3 km |
Land at Heywood Grange Solar Photovoltaics · Operational | 8.4 | 7.8 km |
Noriker Power Staunch Battery · Operational | 20 | 8 km |
Meece Landfill Landfill Gas · Operational | 1.3 | 8.7 km |
Lower Newton Farm Solar Photovoltaics · Operational | 11.5 | 10.6 km |
How big is Screwfix Direct?
Screwfix Direct has a recorded installed capacity of 2.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Screwfix Direct?
REPD records the operator as Kingfisher Scottish Limited Partnership. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Screwfix Direct approved and built?
The application was submitted on 2015-10-08. Permission was granted on 2015-11-03, 1 months later. The site became operational on 2016-01-12, 2 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5828.