Renewable sites › Screwfix Direct
Screwfix Direct
Screwfix Direct is an operational 2.5 MW solar farm in Stoke-on-Trent, generating since 12 January 2016. Planning permission was granted on 3 November 2015, 1 months after submission. Operator of record: Kingfisher Scottish Limited Partnership.
Planning and build timeline
| Application submitted | 8 October 2015 |
| Permission granted | 3 November 2015 1 months after submission |
| Operational | 12 January 2016 2 months after consent |
Screening a site of your own?
Stoke-on-Trent approves 95% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Screwfix Direct’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Stoke-on-Trent’s record on solar
Stoke-on-Trent has decided 19 solar farms and approved 95%, taking a median of 1.7 months. See every solar farm decision in Stoke-on-Trent →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
EfW Incineration · Operational | 14.2 | 1.7 km |
Solar Photovoltaics · Operational | 4.4 | 6.3 km |
Battery · Operational | — | 6.3 km |
Wind Onshore · Operational | 1.9 | 7.3 km |
Solar Photovoltaics · Operational | 8.4 | 7.8 km |
Battery · Operational | 20 | 8 km |
Landfill Gas · Operational | 1.3 | 8.7 km |
Solar Photovoltaics · Operational | 11.5 | 10.6 km |
How big is Screwfix Direct?
Screwfix Direct has a recorded installed capacity of 2.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Screwfix Direct?
REPD records the operator as Kingfisher Scottish Limited Partnership. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Screwfix Direct approved and built?
The application was submitted on 8 October 2015. Permission was granted on 3 November 2015, 1 months later. The site became operational on 12 January 2016, 2 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5828.