Novarly ParcelRenewable sites

Renewable sitesMarshborough Farm solar park

Marshborough Farm solar park

Marshborough Farm solar park is an operational 5 MW solar farm in Dover, generating since 15 November 2015. Planning permission was granted on 29 May 2015, 3 months after submission. Operator of record: Vogt Solar.

5 MW
Capacity
as recorded in REPD
Operational
Status
since 15 November 2015
Solar Photovoltaics
Technology
Vogt Solar
Dover
Authority
England

Planning and build timeline

Application submitted14 February 2015
Permission granted29 May 2015
3 months after submission
Operational15 November 2015
6 months after consent

Screening a site of your own?

RedlineUK · £39

Dover approves 88% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Marshborough Farm solar park’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 1 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Dover’s record on solar

Dover has decided 16 solar farms and approved 88%, taking a median of 3.7 months. See every solar farm decision in Dover

Other built sites within 15 km

SiteMWDistance
Biomass (dedicated) · Operational
162.8 km
Solar Photovoltaics · Operational
54.3 km
Battery · Under Construction
49.94.3 km
Battery · Operational
49.94.6 km
Battery · Operational
50.14.6 km
Battery · Under Construction
2494.7 km
Solar Photovoltaics · Operational
4.95 km
Solar Photovoltaics · Operational
15.4 km

How big is Marshborough Farm solar park?

Marshborough Farm solar park has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Marshborough Farm solar park?

REPD records the operator as Vogt Solar. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Marshborough Farm solar park approved and built?

The application was submitted on 14 February 2015. Permission was granted on 29 May 2015, 3 months later. The site became operational on 15 November 2015, 6 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5117.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode