Renewable sitesRichborough Energy Park - Phase 3 (Sheaf)

Richborough Energy Park - Phase 3 (Sheaf)

Richborough Energy Park - Phase 3 (Sheaf) is under construction in Thanet with a recorded capacity of 249 MW.

249 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Battery
Technology
Pacific Green
Thanet
Authority
England

Planning and build timeline

Application submitted2022-04-25
Permission granted2022-09-22
5 months after submission
Operationalnot recorded

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Thanet’s record on battery storage

Thanet has decided 7 battery storage schemes and approved 100%, taking a median of 6.3 months. See every battery storage scheme decision in Thanet

Other built sites within 15 km

SiteMWDistance
Richborough Energy Park
Battery · Operational
49.90.3 km
Richborough Energy Park - Phase 2
Battery · Operational
50.10.3 km
Ebbsfleet Farm Solar Farm
Solar Photovoltaics · Operational
4.90.4 km
Ebbsfleet Solar Farm
Solar Photovoltaics · Operational
50.6 km
Harrington Franklin, Richborough Energy Park - Battery Storage
Battery · Under Construction
49.90.7 km
Minster Abbey, Bedlam Court Lane - Solar PV panels
Solar Photovoltaics · Under Construction
333 km
Thorne Farm
Solar Photovoltaics · Operational
6.23 km
Discovery Park
Biomass (dedicated) · Operational
163.1 km

How big is Richborough Energy Park - Phase 3 (Sheaf)?

Richborough Energy Park - Phase 3 (Sheaf) has a recorded installed capacity of 249 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Richborough Energy Park - Phase 3 (Sheaf)?

REPD records the operator as Pacific Green. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Richborough Energy Park - Phase 3 (Sheaf) approved and built?

The application was submitted on 2022-04-25. Permission was granted on 2022-09-22, 5 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 11201.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council