Renewable sitesRichborough Energy Park - Phase 3 (Sheaf)

Richborough Energy Park - Phase 3 (Sheaf)

Richborough Energy Park - Phase 3 (Sheaf) is a 249 MW battery storage site under construction in Thanet. Planning permission was granted on 22 September 2022, 5 months after submission. Operator of record: Pacific Green.

249 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Battery
Technology
Pacific Green
Thanet
Authority
England

Planning and build timeline

Application submitted25 April 2022
Permission granted22 September 2022
5 months after submission
Operationalnot recorded

Screening a site of your own?

RedlineUK · £39

Thanet approves 100% of battery storage schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Richborough Energy Park - Phase 3 (Sheaf)’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented battery storage scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Thanet’s record on battery storage

Thanet has decided 7 battery storage schemes and approved 100%, taking a median of 6.3 months. See every battery storage scheme decision in Thanet

Other built sites within 15 km

SiteMWDistance
Battery · Operational
49.90.3 km
Battery · Operational
50.10.3 km
Solar Photovoltaics · Operational
4.90.4 km
Solar Photovoltaics · Operational
50.6 km
Battery · Under Construction
49.90.7 km
Solar Photovoltaics · Under Construction
333 km
Solar Photovoltaics · Operational
6.23 km
Biomass (dedicated) · Operational
163.1 km

How big is Richborough Energy Park - Phase 3 (Sheaf)?

Richborough Energy Park - Phase 3 (Sheaf) has a recorded installed capacity of 249 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Richborough Energy Park - Phase 3 (Sheaf)?

REPD records the operator as Pacific Green. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Richborough Energy Park - Phase 3 (Sheaf) approved and built?

The application was submitted on 25 April 2022. Permission was granted on 22 September 2022, 5 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 11201.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode