Renewable sitesEbbsfleet Farm Solar Farm

Ebbsfleet Farm Solar Farm

Ebbsfleet Farm Solar Farm is operational in Thanet with a recorded capacity of 4.9 MW, and has been generating since 2011-09-05.

4.9 MW
Capacity
as recorded in REPD
Operational
Status
since 2011-09-05
Solar Photovoltaics
Technology
GKA Limited
Thanet
Authority
England

Planning and build timeline

Application submitted2011-01-31
Permission granted2011-03-18
2 months after submission
Operational2011-09-05
6 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Thanet’s record on solar

Thanet has decided 20 solar farms and approved 95%, taking a median of 2.3 months. See every solar farm decision in Thanet

Other built sites within 15 km

SiteMWDistance
Richborough Energy Park - Phase 3 (Sheaf)
Battery · Under Construction
2490.4 km
Richborough Energy Park
Battery · Operational
49.90.5 km
Richborough Energy Park - Phase 2
Battery · Operational
50.10.5 km
Ebbsfleet Solar Farm
Solar Photovoltaics · Operational
50.8 km
Harrington Franklin, Richborough Energy Park - Battery Storage
Battery · Under Construction
49.91.1 km
Thorne Farm
Solar Photovoltaics · Operational
6.22.6 km
Minster Abbey, Bedlam Court Lane - Solar PV panels
Solar Photovoltaics · Under Construction
332.6 km
Discovery Park
Biomass (dedicated) · Operational
163.5 km

How big is Ebbsfleet Farm Solar Farm?

Ebbsfleet Farm Solar Farm has a recorded installed capacity of 4.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Ebbsfleet Farm Solar Farm?

REPD records the operator as GKA Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Ebbsfleet Farm Solar Farm approved and built?

The application was submitted on 2011-01-31. Permission was granted on 2011-03-18, 2 months later. The site became operational on 2011-09-05, 6 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1041.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council