Novarly ParcelRenewable planning

Renewable planning SolarDover

Solar planning in Dover

Dover has decided 16 solar farms and approved 88% of them, taking a median of 3.7 months to decide. Consented capacity: 69 MW. 4 applications still awaiting a decision.

88%
Approved
14 granted · 2 refused
3.7 mo
Median decision
UK 2.3 mo
69 MW
Consented
38 MW refused
2
Appeals
0 allowed on appeal

How Dover compares

Against the 298 UK authorities with 5+ solar decisions, Dover sits in the 21st percentile for approval rate (5 points below the England average) and the 19th percentile for speed.

Decisions by year

35Approved — 1 (2013)113Approved — 3 (2014)Refused — 1 (2014)414Approved — 2 (2015)Refused — 1 (2015)315Approved — 1 (2016)116Approved — 2 (2021)221Approved — 3 (2022)322Approved — 1 (2023)123Approved — 1 (2026)126
Approved Refused

Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (22)

SchemeMWStatusDecided
Priory Court, St Johns Road - Solar Panels
Home Office · 26/00127
0.28Application Submitted2026-02-06
Guilton Farm, Ash - Solar Panels
Mansfield · 25/01300 · 1.8 mo to decide
0.27Application Submitted2026-01-29
West Street - Solar Panels
Sainsburys Supermarkets Limited · 25/01336 · 1.3 mo to decide
0.24Awaiting Construction2026-01-23
Guilton Farm, Guilton - Solar Panels
FW & MF Mansfield Property Investments Limited · 25/00553
0.41Application Withdrawn2025-06-25
Elvington Solar Farm
Pathfinder Clean Energy UK Limited · 25/00709
49.5Application Submitted2025-06-21
Richborough Energy Park, Ramsgate Road - Solar Panels
Nemo Link · PN12/TH/23/1104 · 1.2 mo to decide
1Awaiting Construction2023-09-22
Chalk Pit Solar Farm
Greentech Services · 22/00668 · 6.1 mo to decide
24Awaiting Construction2022-11-25
Richborough Solar Farm - Solar Farm
Thanet Solar Limited · 21/01045 · 10 mo to decide
Awaiting Construction2022-05-13
Westmount Education Centre
Blackap Limited · 20/01355 · 14.5 mo to decide
0.26Awaiting Construction2022-02-03
Kedleston Road Solar Panels
Standard Life Investments · 20/01492 · 1.8 mo to decide
0.5Awaiting Construction2021-02-03
Old Lorry Farm Shop
Old Lorry Farm Shop · 20/01253 · 2.1 mo to decide
Under Construction2021-01-20
Snowdown Colliery
BNRG Renewables UK · 15/00777 · 5.3 mo to decide
5Planning Permission Expired2016-01-28
Chapmans Hill
BNRG Renewables · 14/00419
7Application Withdrawn2015-11-13
The Engine Shed Field
Lumicity · 13/01106 · 20.8 mo to decide
11Appeal Refused2015-09-18
Marshborough Farm solar park
Vogt Solar · 15/00115 · 3.4 mo to decide
5Operational2015-05-29
Land At Guston Court Farm
Conergy West Sussex · 14/01133 · 3.1 mo to decide
5Operational2015-03-19
Guston Court Farm
Guston A Solar Farm Ltd & Guston C Solar Farm Ltd · 14/00153 · 7.2 mo to decide
27Application Refused2014-09-26
Tilmanstone Colliery
Ovenden Plant Hire Limited · 13/00654 · 6.9 mo to decide
10Operational2014-03-12
Grain Harvesters Ltd
Grain Harvesters Ltd · 13/01006 · 3 mo to decide
1Operational2014-03-06
Ebbsfleet Solar Farm
Thanet Solar Ltd/ Vogt Solar · 13/00794 · 3.9 mo to decide
5Operational2014-01-24
Home Farm (Knowlton - solar)
Sunsave 20 (Knowlton) Ltd/ Vogt Solar · 13/00405 · 4.4 mo to decide
11.5Operational2013-10-07
Marshborough Farm solar park
Vogt Solar · 13/00332 · 3.3 mo to decide
12.8Revised2013-08-13

Does Dover approve solar farms?

Yes — of the 16 solar farms Dover has decided, 88% were approved (14 granted, 2 refused). The UK-wide rate for solar is 93%.

How long does a solar farm application take in Dover?

The median time from application to decision is 3.7 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much solar capacity has Dover consented?

69 MW has been consented across 14 approved schemes, with 38 MW refused. A further 4 applications awaits a decision.

Other technologies in Dover

Battery storage in DoverOnshore wind in Dover

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.

Novarly Parcel · official public data, read properly · parcel.novarly.com