Harrington Franklin, Richborough Energy Park - Battery Storage is under construction in Dover with a recorded capacity of 49.9 MW.
Planning and build timeline
| Application submitted | 2022-06-01 |
| Permission granted | 2022-12-06 6 months after submission |
| Operational | not recorded |
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Richborough Energy Park - Phase 3 (Sheaf) Battery · Under Construction | 249 | 0.7 km |
Richborough Energy Park - Phase 2 Battery · Operational | 50.1 | 0.8 km |
Richborough Energy Park Battery · Operational | 49.9 | 0.8 km |
Ebbsfleet Solar Farm Solar Photovoltaics · Operational | 5 | 0.8 km |
Ebbsfleet Farm Solar Farm Solar Photovoltaics · Operational | 4.9 | 1.1 km |
Discovery Park Biomass (dedicated) · Operational | 16 | 2.5 km |
Minster Abbey, Bedlam Court Lane - Solar PV panels Solar Photovoltaics · Under Construction | 33 | 3.5 km |
Thorne Farm Solar Photovoltaics · Operational | 6.2 | 3.6 km |
How big is Harrington Franklin, Richborough Energy Park - Battery Storage?
Harrington Franklin, Richborough Energy Park - Battery Storage has a recorded installed capacity of 49.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Harrington Franklin, Richborough Energy Park - Battery Storage?
REPD records the operator as EDP Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Harrington Franklin, Richborough Energy Park - Battery Storage approved and built?
The application was submitted on 2022-06-01. Permission was granted on 2022-12-06, 6 months later. The site is recorded as under construction and has no operational date yet.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 11449.
Novarly Parcel · official public data, read properly · parcel.novarly.com