Harrington Franklin, Richborough Energy Park - Battery Storage

Harrington Franklin, Richborough Energy Park - Battery Storage is a 49.9 MW battery storage site under construction in Dover. Planning permission was granted on 6 December 2022, 6 months after submission. Operator of record: EDP Renewables.

49.9 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Battery
Technology
EDP Renewables
Dover
Authority
England

Planning and build timeline

Application submitted1 June 2022
Permission granted6 December 2022
6 months after submission
Operationalnot recorded

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Dover: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Harrington Franklin, Richborough Energy Park - Battery Storage’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented battery storage scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Other built sites within 15 km

SiteMWDistance
Battery · Under Construction
2490.7 km
Battery · Operational
50.10.8 km
Battery · Operational
49.90.8 km
Solar Photovoltaics · Operational
50.8 km
Solar Photovoltaics · Operational
4.91.1 km
Biomass (dedicated) · Operational
162.5 km
Solar Photovoltaics · Under Construction
333.5 km
Solar Photovoltaics · Operational
6.23.6 km

How big is Harrington Franklin, Richborough Energy Park - Battery Storage?

Harrington Franklin, Richborough Energy Park - Battery Storage has a recorded installed capacity of 49.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Harrington Franklin, Richborough Energy Park - Battery Storage?

REPD records the operator as EDP Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Harrington Franklin, Richborough Energy Park - Battery Storage approved and built?

The application was submitted on 1 June 2022. Permission was granted on 6 December 2022, 6 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 11449.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode