Renewable sites › Discovery Park
Discovery Park
Discovery Park is operational in Dover with a recorded capacity of 16 MW, and has been generating since 2018-09-28.
Planning and build timeline
| Application submitted | 2013-08-23 |
| Permission granted | 2013-10-18 2 months after submission |
| Operational | 2018-09-28 59 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Harrington Franklin, Richborough Energy Park - Battery Storage Battery · Under Construction | 49.9 | 2.5 km |
Marshborough Farm solar park Solar Photovoltaics · Operational | 5 | 2.8 km |
Ebbsfleet Solar Farm Solar Photovoltaics · Operational | 5 | 3 km |
Richborough Energy Park - Phase 2 Battery · Operational | 50.1 | 3.1 km |
Richborough Energy Park Battery · Operational | 49.9 | 3.1 km |
Richborough Energy Park - Phase 3 (Sheaf) Battery · Under Construction | 249 | 3.1 km |
Ebbsfleet Farm Solar Farm Solar Photovoltaics · Operational | 4.9 | 3.5 km |
Old Lorry Farm Shop Solar Photovoltaics · Under Construction | — | 5.6 km |
How big is Discovery Park?
Discovery Park has a recorded installed capacity of 16 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Discovery Park?
REPD records the operator as Burmeister & Wain Scandinavian Contractor (BWSC). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Discovery Park approved and built?
The application was submitted on 2013-08-23. Permission was granted on 2013-10-18, 2 months later. The site became operational on 2018-09-28, 59 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 173.