Marsh House Solar Park

Marsh House Solar Park is an operational 5.5 MW solar farm in East Hampshire, generating since 21 March 2015. Planning permission was granted on 23 December 2013, 22 months after submission. Operator of record: Constantine Land Ltd.

5.5 MW
Capacity
as recorded in REPD
Operational
Status
since 21 March 2015
Solar Photovoltaics
Technology
Constantine Land Ltd
East Hampshire
Authority
England

Planning and build timeline

Application submitted6 March 2012
Permission granted23 December 2013
22 months after submission
Operational21 March 2015
15 months after consent

Screening a site of your own?

RedlineUK · £39

East Hampshire approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Marsh House Solar Park’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

East Hampshire’s record on solar

East Hampshire has decided 16 solar farms and approved 100%, taking a median of 2.9 months. See every solar farm decision in East Hampshire

Other built sites within 15 km

SiteMWDistance
Landfill Gas · Operational
2.41.8 km
Landfill Gas · Operational
1.26.2 km
Solar Photovoltaics · Operational
58.5 km
Solar Photovoltaics · Operational
5.99.5 km
Solar Photovoltaics · Operational
1.710 km
Solar Photovoltaics · Operational
1110 km
Solar Photovoltaics · Operational
1110 km
Solar Photovoltaics · Under Construction
1.1510.2 km

How big is Marsh House Solar Park?

Marsh House Solar Park has a recorded installed capacity of 5.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Marsh House Solar Park?

REPD records the operator as Constantine Land Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Marsh House Solar Park approved and built?

The application was submitted on 6 March 2012. Permission was granted on 23 December 2013, 22 months later. The site became operational on 21 March 2015, 15 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1233.