Renewable sites › Farnham Landfill
Farnham Landfill
Farnham Landfill is operational in Waverley with a recorded capacity of 2.4 MW, and has been generating since 2004-01-01.
Planning and build timeline
| Application submitted | 1999-02-15 |
| Permission granted | 2002-08-13 42 months after submission |
| Operational | 2004-01-01 17 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 4 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Marsh House Solar Park Solar Photovoltaics · Operational | 5.5 | 1.8 km |
Runfold Landfill Landfill Gas · Operational | 1.2 | 5.2 km |
Hungerford Farm Solar Photovoltaics · Operational | 5 | 10.1 km |
Farnborough International Exhibition Centre, Etps Road - Solar Panels Solar Photovoltaics · Under Construction | 1.15 | 10.4 km |
Farnborough Airport - Solar Panels Solar Photovoltaics · Operational | 1.7 | 10.4 km |
Land to the north and south of Cakers Lane (Wilsom) Solar Photovoltaics · Operational | 11 | 10.4 km |
Wilsom Farm Solar Photovoltaics · Operational | 11 | 10.4 km |
Taplins Farm solar park Solar Photovoltaics · Operational | 5.9 | 11 km |
How big is Farnham Landfill?
Farnham Landfill has a recorded installed capacity of 2.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Farnham Landfill?
REPD records the operator as Biffa. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Farnham Landfill approved and built?
The application was submitted on 1999-02-15. Permission was granted on 2002-08-13, 42 months later. The site became operational on 2004-01-01, 17 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 594.