Novarly ParcelRenewable planning

Renewable planning SolarEast Hampshire

Solar planning in East Hampshire

East Hampshire has decided 16 solar farms and approved 100% of them, taking a median of 2.9 months to decide. Consented capacity: 95 MW. 6 applications still awaiting a decision.

100%
Approved
16 granted · 0 refused
2.9 mo
Median decision
UK 2.3 mo
95 MW
Consented
across approved schemes
2
Appeals
2 allowed on appeal

How East Hampshire compares

Against the 298 UK authorities with 5+ solar decisions, East Hampshire sits in the 77th percentile for approval rate (7 points above the England average) and the 36th percentile for speed.

Decisions by year

35Approved — 1 (2012)112Approved — 1 (2013)113Approved — 2 (2014)214Approved — 2 (2015)215Approved — 1 (2016)116Approved — 1 (2022)122Approved — 2 (2023)223Approved — 3 (2024)324Approved — 2 (2025)225Approved — 1 (2026)126
Approved Refused

Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (22)

SchemeMWStatusDecided
Little Willow, Upper Anstey Lane - Solar Array
Private Developer · EHDC-25-0030-FUL · 13.8 mo to decide
0.44Awaiting Construction2026-02-26
Gaston Lane, Farringdon - Solar Farm & Battery Storage
Quintas Energy UK Limited · EHDC-25-0716-FUL
44Application Submitted2025-06-19
Alton Sport Centre - Solar Panels
East Hampshire District Council · EHDC-25-0434-FUL · 2.3 mo to decide
0.37Operational2025-06-10
Alton Sport Centre - Solar Panels
East Hampshire District Council · EHDC-25-0011-PA2J
0.37Revised2025-04-10
Maltbys Engineering, Newman Lane - Solar Panels
PHL (UK)Limited · EHDC-24-0011-PA2J · 2.4 mo to decide
Awaiting Construction2025-03-04
Reeves Britannia, The Causeway - Solar PV panels
Energise South Downs · SDNP/24/04633/PA14J · 1.5 mo to decide
0.16Awaiting Construction2024-12-23
Sandhill Farm, Picketts Hill - Solar panels
Knightsbridge Farms Limited · 27877/026 · 23.1 mo to decide
0.44Awaiting Construction2024-10-02
Spire Portsmouth Hospital, Bartons Road - Solar Pv Panels
Spire Portsmouth Hospital · 26978/022 · 1.6 mo to decide
0.15Awaiting Construction2024-04-26
Old Thorns Golf and Country Club - Solar Panels
Old Thorns Golf & Country Club · 21589/114 · 1.6 mo to decide
0.22Awaiting Construction2023-03-24
Copse Close Solar Farm
Copse Close Solar Farm Limited · 55506/002 · 10.6 mo to decide
49.9Awaiting Construction2023-02-06
The New Barn, Bedford Road - Solar Panels
East Hampshire District Council · SDNP/22/04640/FUL · 1.9 mo to decide
0.17Awaiting Construction2022-12-02
Lovedean, Denmead - Solar farm & Battery storage
Lovedean Green Limited · 58038/003
49.9Application Submitted2022-03-11
Steyne Farm - Solar Panels
Private Developer · 27613/020
Application Submitted2021-01-21
Whitman Laboratories
Whitman Laboratories · SDNP/16/03016/FUL · 1.8 mo to decide
1Operational2016-08-23
Land to the north and south of Cakers Lane (Wilsom)
Canadian Solar · 55465/001 · 9.4 mo to decide
11Operational2015-11-02
Wilsom Farm
Canadian solar · 55465/001 · 9.4 mo to decide
11Operational2015-11-02
Land east of Kingsley Sports Club
Granite Solar · 52947/002 · 3 mo to decide
5Planning Permission Expired2014-04-30
Barley Wood Farm Lane
Lightsource Renewable Energy · 54507/002 · 3.7 mo to decide
5.4Operational2014-03-31
Marsh House Solar Park
Constantine Land Ltd · 53234/001 · 21.6 mo to decide
5.5Operational2013-12-23
Gaston Lane
Lightsource Renewable Energy · 54507/001
5.8Revised2013-08-14
Land east of Kingsley Sports Club
Granite Consultants Limited · 52947/001
5Revised2013-02-07
Lovedean Farm
Lightsource Renewable Energy · 54495/001 · 2.7 mo to decide
4.5Operational2012-12-24

Does East Hampshire approve solar farms?

Yes — of the 16 solar farms East Hampshire has decided, 100% were approved (16 granted, 0 refused). The UK-wide rate for solar is 93%.

How long does a solar farm application take in East Hampshire?

The median time from application to decision is 2.9 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much solar capacity has East Hampshire consented?

95 MW has been consented across 16 approved schemes. A further 6 applications awaits a decision.

Other technologies in East Hampshire

Battery storage in East HampshireOnshore wind in East Hampshire

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.