Renewable sitesHadyard Hill

Hadyard Hill

Hadyard Hill is an operational 120 MW onshore wind farm in Scotland, generating since 8 May 2006. Planning permission was granted on 29 December 2003, 7 months after submission. Operator of record: Scottish and Southern Energy (SSE).

120 MW
Capacity
as recorded in REPD
Operational
Status
since 8 May 2006
Wind Onshore
Technology
Scottish and Southern Energy (SSE)
National
Authority
Scotland

Planning and build timeline

Application submitted27 May 2003
Permission granted29 December 2003
7 months after submission
Operational8 May 2006
28 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the same record on your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Hadyard Hill’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Scottish Government (S36)’s record on onshore wind

Scottish Government (S36) has decided 173 onshore wind schemes and approved 80%, taking a median of 33.7 months. See every onshore wind scheme decision in Scottish Government (S36)

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
254.5 km
Wind Onshore · Operational
204.8 km
Wind Onshore · Operational
18.85.5 km
Wind Onshore · Operational
4214.1 km
Wind Onshore · Operational
5614.3 km

How big is Hadyard Hill?

Hadyard Hill has a recorded installed capacity of 120 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Hadyard Hill?

REPD records the operator as Scottish and Southern Energy (SSE). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Hadyard Hill approved and built?

The application was submitted on 27 May 2003. Permission was granted on 29 December 2003, 7 months later. The site became operational on 8 May 2006, 28 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3109.