Renewable sites › Tralorg Wind Farm
Tralorg Wind Farm
Tralorg Wind Farm is operational in South Ayrshire with a recorded capacity of 20 MW, and has been generating since 2020-06-01.
Planning and build timeline
| Application submitted | 2011-02-10 |
| Permission granted | 2014-02-21 36 months after submission |
| Operational | 2020-06-01 75 months after consent |
South Ayrshire’s record on onshore wind
South Ayrshire has decided 12 onshore wind schemes and approved 33%, taking a median of 24.6 months. See every onshore wind scheme decision in South Ayrshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Assel Valley Wind Farm Wind Onshore · Operational | 25 | 3.1 km |
Hadyard Hill Wind Onshore · Operational | 120 | 4.8 km |
Kirk Hill Wind Farm Wind Onshore · Operational | 18.8 | 7.6 km |
Dalquhandy Windfarm Wind Onshore · Operational | 42 | 10.1 km |
Mark Hill Wind Onshore · Operational | 56 | 14 km |
How big is Tralorg Wind Farm?
Tralorg Wind Farm has a recorded installed capacity of 20 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Tralorg Wind Farm?
REPD records the operator as RPMI Railpen (formerly BayWa). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Tralorg Wind Farm approved and built?
The application was submitted on 2011-02-10. Permission was granted on 2014-02-21, 36 months later. The site became operational on 2020-06-01, 75 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4073.
Novarly Parcel · official public data, read properly · parcel.novarly.com