Renewable sites › Long Lane Solar Farm / Nottingham Brick Works
Long Lane Solar Farm / Nottingham Brick Works
Long Lane Solar Farm / Nottingham Brick Works is a 17 MW solar farm under construction in Broxtowe. Planning permission was granted on 11 November 2015, 4 months after submission. Operator of record: Earthworm/ EW Capital.
Planning and build timeline
| Application submitted | 22 July 2015 |
| Permission granted | 11 November 2015 4 months after submission |
| Operational | not recorded |
Screening a site of your own?
Redline runs the record on your own boundary in Broxtowe: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Long Lane Solar Farm / Nottingham Brick Works’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
- Green Belt — Broxtowe
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Advanced Conversion Technologies · Under Construction | 29.5 | 1.5 km |
Wind Onshore · Operational | 2.5 | 4.8 km |
Wind Onshore · Operational | 1.5 | 6.6 km |
Solar Photovoltaics · Operational | 0.62 | 7.3 km |
Landfill Gas · Operational | 1.8 | 7.6 km |
Landfill Gas · Operational | 2.8 | 8 km |
Anaerobic Digestion · Operational | — | 8.4 km |
Solar Photovoltaics · Operational | 0.35 | 9.3 km |
How big is Long Lane Solar Farm / Nottingham Brick Works?
Long Lane Solar Farm / Nottingham Brick Works has a recorded installed capacity of 17 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Long Lane Solar Farm / Nottingham Brick Works?
REPD records the operator as Earthworm/ EW Capital. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Long Lane Solar Farm / Nottingham Brick Works approved and built?
The application was submitted on 22 July 2015. Permission was granted on 11 November 2015, 4 months later. The site is recorded as under construction and has no operational date yet.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5603.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode