Novarly ParcelRenewable sites

Renewable sitesLlanwern Solar Farm & Battery Storage

Llanwern Solar Farm & Battery Storage

Llanwern Solar Farm & Battery Storage is operational in Wales with a recorded capacity of 75 MW, and has been generating since 2021-03-01.

75 MW
Capacity
as recorded in REPD
Operational
Status
since 2021-03-01
Solar Photovoltaics
Technology
NextEnergy Capital LLP
National
Authority
Wales

Planning and build timeline

Application submitted2018-02-20
Permission granted2018-11-13
9 months after submission
Operational2021-03-01
28 months after consent

Welsh Government (NSIP)’s record on solar

Welsh Government (NSIP) has decided 23 solar farms and approved 87%, taking a median of 14.2 months. See every solar farm decision in Welsh Government (NSIP)

Other built sites within 15 km

SiteMWDistance
Llanwern Solar Farm & Battery Storage
Battery · Operational
2.3 km
Uskmouth Power Station
Biomass (co-firing) · Operational
183.5 km
Uskmouth Power Station - Battery Storage
Battery · Under Construction
2303.5 km
Longlands Farm, Rush Wall Lane
Wind Onshore · Operational
3.53.9 km
Geraint Thomas National Velodrome - Solar
Solar Photovoltaics · Operational
4 km
Nash Waste Water Treatment Works Turbine
Wind Onshore · Operational
2.54 km
Liberty Steel Power Station
Biomass (dedicated) · Operational
94.1 km
Solutia UK Ltd
Wind Onshore · Operational
54.2 km

How big is Llanwern Solar Farm & Battery Storage?

Llanwern Solar Farm & Battery Storage has a recorded installed capacity of 75 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Llanwern Solar Farm & Battery Storage?

REPD records the operator as NextEnergy Capital LLP. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Llanwern Solar Farm & Battery Storage approved and built?

The application was submitted on 2018-02-20. Permission was granted on 2018-11-13, 9 months later. The site became operational on 2021-03-01, 28 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6411.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council