Llanwern Solar Farm & Battery Storage

Llanwern Solar Farm & Battery Storage is an operational 75 MW solar farm in Wales, generating since 1 March 2021. Planning permission was granted on 13 November 2018, 9 months after submission. Operator of record: NextEnergy Capital LLP.

75 MW
Capacity
as recorded in REPD
Operational
Status
since 1 March 2021
Solar Photovoltaics
Technology
NextEnergy Capital LLP
National
Authority
Wales

Planning and build timeline

Application submitted20 February 2018
Permission granted13 November 2018
9 months after submission
Operational1 March 2021
28 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the same record on your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Llanwern Solar Farm & Battery Storage’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Welsh Government (NSIP)’s record on solar

Welsh Government (NSIP) has decided 23 solar farms and approved 87%, taking a median of 14.2 months. See every solar farm decision in Welsh Government (NSIP)

Other built sites within 15 km

SiteMWDistance
Battery · Operational
2.3 km
Battery · Under Construction
2303.5 km
Biomass (co-firing) · Operational
183.5 km
Wind Onshore · Operational
3.53.9 km
Solar Photovoltaics · Operational
4 km
Wind Onshore · Operational
2.54 km
Biomass (dedicated) · Operational
94.1 km
Wind Onshore · Operational
54.2 km

How big is Llanwern Solar Farm & Battery Storage?

Llanwern Solar Farm & Battery Storage has a recorded installed capacity of 75 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Llanwern Solar Farm & Battery Storage?

REPD records the operator as NextEnergy Capital LLP. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Llanwern Solar Farm & Battery Storage approved and built?

The application was submitted on 20 February 2018. Permission was granted on 13 November 2018, 9 months later. The site became operational on 1 March 2021, 28 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6411.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode