Renewable planning › Solar › Welsh Government (NSIP)
Solar planning in Welsh Government (NSIP)
Welsh Government (NSIP) has decided 23 solar farms and approved 87% of them, taking a median of 14.2 months to decide. Consented capacity: 834 MW. 14 applications still awaiting a decision.
How Welsh Government (NSIP) compares
Against the 298 UK authorities with 5+ solar decisions, Welsh Government (NSIP) sits in the 18th percentile for approval rate (6 points below the England average) and the 1st percentile for speed.
Decisions by year
Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (37)
| Scheme | MW | Status | Decided |
|---|---|---|---|
White House Farm Qair UK · CAS-03107-C5X9W1 | 30 | Application Submitted | 2025-12-30 |
Convatec Green Manufacturing Hub Convatec Limited · CAS-02977-Y9F1W7 · 7.6 mo to decide | 5 | Application Refused | 2025-11-19 |
Pencoed Ganol Farm, Pendderi Road - Solar Panels Windel Solar 11 Limited · CAS-04012-T8Y8D2 | 35 | Application Submitted | 2025-11-11 |
Craig y Perthi Solar Farm JBM Solar Projects Limited · DNS/3279787 · 18.3 mo to decide | 99.9 | Application Refused | 2025-10-21 |
Alaw M�n Solar Farm - Solar Farm & Energy Storage Facility Enso Energy Limited · DNS/3274702 · 15.3 mo to decide | 160 | Awaiting Construction | 2025-08-26 |
Land at Pen Onn - Solar Farm Iolo Energy · DNS/3273713 · 17.3 mo to decide | 45 | Awaiting Construction | 2025-05-29 |
Glyntaff Solar Farm, Bryntail Road - Solar Array Renantis Falck Renewables Limited · CAS-03147-D7S9P8 | 39.9 | Application Submitted | 2025-05-09 |
Pencaerlan Solar Farm Greentech Projects Holding UK Limited · DNS/3272424 | 25 | Application Submitted | 2025-04-30 |
Penllergaer Solar Farm - Solar Farm Ecap Renewables · CAS-03127-J6W2K0 | 40 | Application Submitted | 2025-04-15 |
Parc Worlton Solar Farm Lightrock Power · CAS-02112-T2N0G8 · 13.9 mo to decide | 42 | Awaiting Construction | 2025-01-21 |
Pentre Bach Solar Farm Elgin Energy EsCo Ltd · DNS/3239190 | 20 | Application Submitted | 2025-01-09 |
Tonmawr - Mynydd Fforch Dwm Wind Farm Naturalis Energy Developments Limited · DNS/3255801 · 13.7 mo to decide | — | Awaiting Construction | 2024-12-23 |
East Aberthaw - Solar farm Low Carbon UK Solar Investment Co Limited · CAS-01391-M3G6Q9 · 13.5 mo to decide | 35 | Awaiting Construction | 2024-12-20 |
Alleston Solar Farm Stantec UK Limited · CAS-03072-D7X6N7 | 30 | Application Submitted | 2024-12-16 |
Craig Y Perchych, Glais - Solar farm Windel Energy · DNS/3279676 · 14.1 mo to decide | 20 | Awaiting Construction | 2024-12-16 |
Parc Solar Caenewydd Infinis Solar Developments · CAS-01900-V0J7C7 · 5.7 mo to decide | 42 | Awaiting Construction | 2024-12-02 |
Ty�n y Waun - Solar Farm (Bridgend Energy Hub) Cenin Renewables Limited · DNS/3279521 · 15.4 mo to decide | 40 | Awaiting Construction | 2024-10-11 |
Mynydd Maen Solar Farm (Cil-Lonydd) Cenin Renewables Limited · DNS CAS-02446-R8X8W2 | 35 | Application Submitted | 2024-07-19 |
Plas Power Estate Solar Farm Lightsource BP · DNS/3253253 | 57 | Application Submitted | 2024-06-11 |
Pancross & Oaklands Solar Farm Infinis · DNS/3245503 · 12.6 mo to decide | 50 | Awaiting Construction | 2024-05-23 |
Vianshill Farm, Parc Dyffryn - Solar Farm & Battery Storage Cenin Renewables Limited · DNS/3267575 · 19.6 mo to decide | 65 | Awaiting Construction | 2024-05-23 |
Cwm Ivor Penyrheol Solar Farm Caerphilly County Borough Council · DNS/3266623 · 15.4 mo to decide | 20 | Awaiting Construction | 2024-05-23 |
Bretton Hall Solar Farm (Wales) YnNi Newydd (New Energy Co-op) · DNS/3251545 · 17.4 mo to decide | 16 | Awaiting Construction | 2023-12-19 |
Brynrhyd Solar Farm Capital Dynamics Limited · DNS/3260565 · 19.7 mo to decide | 36 | Awaiting Construction | 2023-06-20 |
Parc Solar Traffwll Low Carbon · DNS/3217391 · 12.9 mo to decide | 35 | Awaiting Construction | 2023-03-17 |
Penpergwm Solar Farm (Great House Farm) Renewable Connections Developments Limited · DNS/3252305 · 11.7 mo to decide | 32 | Under Construction | 2023-01-17 |
Maes Mawr Solar Elgin Energy EsCo Ltd · DNS/3282038 | 30 | Application Submitted | 2022-12-01 |
Brynwell Farm Brynwell Farm Solar Limited · DNS/3261558 · 18.7 mo to decide | 21 | Awaiting Construction | 2022-11-10 |
Elwy Solar Energy Farm Statkraft UK Limited · DNS/3247619 · 15.3 mo to decide | 62 | Application Refused | 2022-07-01 |
Wentlooge Renewable Energy Hub Wentlooge Farmers' Solar Scheme · CAS-01772-Z5P5D2 | 125 | Appeal Lodged | 2022-06-20 |
Rush Wall Solar Park Rush Wall Solar Park · DNS/3220457 | 75 | Appeal Lodged | 2022-03-18 |
Blackberry Lane Wessex Solar Energy · DNS/3245065 · 9.4 mo to decide | 22 | Revised | 2021-10-27 |
Tycroes Solar Farm Spring Dev 2 · DNS/3227364 · 14.3 mo to decide | 40 | Awaiting Construction | 2021-08-12 |
Llangennech Solar Voltalia UK · DNS/3213164 · 16.1 mo to decide | 29.9 | Awaiting Construction | 2021-07-23 |
Wentlooge Renewable Energy Hub Wentlooge Farmers' Solar Scheme · DNS/3216558 | 62.5 | Revised | 2020-05-07 |
Wauntysswg Farm, near Tredagar Elgin Energy · DNS/3213639 · 12.1 mo to decide | 30 | Awaiting Construction | 2019-08-01 |
Llanwern Solar Farm & Battery Storage NextEnergy Capital LLP · DNS/3213968 · 8.7 mo to decide | 75 | Operational | 2018-11-13 |
Does Welsh Government (NSIP) approve solar farms?
Yes — of the 23 solar farms Welsh Government (NSIP) has decided, 87% were approved (20 granted, 3 refused). The UK-wide rate for solar is 93%.
How long does a solar farm application take in Welsh Government (NSIP)?
The median time from application to decision is 14.2 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much solar capacity has Welsh Government (NSIP) consented?
834 MW has been consented across 20 approved schemes, with 167 MW refused. A further 14 applications awaits a decision.
Other technologies in Welsh Government (NSIP)
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.