Renewable sites › Cwm Derwyn Farm
Cwm Derwyn Farm
Cwm Derwyn Farm is operational in Vale of Glamorgan with a recorded capacity of 5 MW, and has been generating since 2017-03-17.
Planning and build timeline
| Application submitted | 2015-06-01 |
| Permission granted | 2015-09-04 3 months after submission |
| Operational | 2017-03-17 18 months after consent |
Vale of Glamorgan’s record on solar
Vale of Glamorgan has decided 25 solar farms and approved 96%, taking a median of 4.2 months. See every solar farm decision in Vale of Glamorgan →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Weycock Road Solar Photovoltaics · Operational | 7 | 0.5 km |
Sutton Mawr Farm Solar Photovoltaics · Operational | 7.5 | 0.9 km |
Whitton Mawr Solar Photovoltaics · Operational | 6 | 2.9 km |
Barry Docks Advanced Conversion Technologies · Operational | 10 | 4.3 km |
Port of Barry - Site 1 Solar Photovoltaics · Operational | 4.5 | 4.7 km |
Port of Barry - Site 2 Solar Photovoltaics · Operational | 5 | 4.7 km |
Llancadle Farm Solar Photovoltaics · Operational | 5 | 5.1 km |
Biglis Farm Solar Photovoltaics · Operational | 5 | 5.3 km |
How big is Cwm Derwyn Farm?
Cwm Derwyn Farm has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Cwm Derwyn Farm?
REPD records the operator as Kronos Solar. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Cwm Derwyn Farm approved and built?
The application was submitted on 2015-06-01. Permission was granted on 2015-09-04, 3 months later. The site became operational on 2017-03-17, 18 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5477.