Novarly ParcelRenewable sites

Renewable sitesWeycock Road

Weycock Road

Weycock Road is an operational 7 MW solar farm in Vale of Glamorgan, generating since 2 March 2016. Planning permission was granted on 1 August 2014, 6 months after submission. Operator of record: Elgin Energy EsCo.

7 MW
Capacity
as recorded in REPD
Operational
Status
since 2 March 2016
Solar Photovoltaics
Technology
Elgin Energy EsCo
Vale of Glamorgan
Authority
Wales

Planning and build timeline

Application submitted22 January 2014
Permission granted1 August 2014
6 months after submission
Operational2 March 2016
19 months after consent

Screening a site of your own?

RedlineUK · £39

Vale of Glamorgan approves 96% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Weycock Road’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Vale of Glamorgan’s record on solar

Vale of Glamorgan has decided 25 solar farms and approved 96%, taking a median of 4.2 months. See every solar farm decision in Vale of Glamorgan

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
50.5 km
Solar Photovoltaics · Operational
7.51.4 km
Solar Photovoltaics · Operational
62.9 km
Advanced Conversion Technologies · Operational
103.9 km
Solar Photovoltaics · Operational
4.54.4 km
Solar Photovoltaics · Operational
54.4 km
Solar Photovoltaics · Operational
54.8 km
Solar Photovoltaics · Operational
55.6 km

How big is Weycock Road?

Weycock Road has a recorded installed capacity of 7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Weycock Road?

REPD records the operator as Elgin Energy EsCo. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Weycock Road approved and built?

The application was submitted on 22 January 2014. Permission was granted on 1 August 2014, 6 months later. The site became operational on 2 March 2016, 19 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2338.