Renewable sitesMount Farm

Mount Farm

Mount Farm is operational in Wychavon with a recorded capacity of 22 MW, and has been generating since 2016-03-23.

22 MW
Capacity
as recorded in REPD
Operational
Status
since 2016-03-23
Solar Photovoltaics
Technology
INRG (Solar Park) 14
Wychavon
Authority
England

Planning and build timeline

Application submitted2014-05-13
Permission granted2015-07-06
14 months after submission
Operational2016-03-23
9 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Wychavon’s record on solar

Wychavon has decided 34 solar farms and approved 97%, taking a median of 4.4 months. See every solar farm decision in Wychavon

Other built sites within 15 km

SiteMWDistance
Sytchwythy Fields
Solar Photovoltaics · Operational
1.43.2 km
The Rainbows Solar Farm
Solar Photovoltaics · Operational
43.4 km
Bypass Nurseries Solar Farm
Solar Photovoltaics · Operational
3.33.5 km
Plant Produce - Solar PV panels
Solar Photovoltaics · Operational
0.153.5 km
Willersey solar farm
Battery · Operational
14.7 km
Littleton Solar Farm
Solar Photovoltaics · Operational
306.3 km
Littleton Solar Farm
Battery · Operational
6.3 km
Norton Hall
Solar Photovoltaics · Operational
2.89 km

How big is Mount Farm?

Mount Farm has a recorded installed capacity of 22 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Mount Farm?

REPD records the operator as INRG (Solar Park) 14. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Mount Farm approved and built?

The application was submitted on 2014-05-13. Permission was granted on 2015-07-06, 14 months later. The site became operational on 2016-03-23, 9 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2175.