Novarly ParcelRenewable sites

Renewable sitesLimberlost Farm

Limberlost Farm

Limberlost Farm is operational in West Berkshire with a recorded capacity of 1.5 MW, and has been generating since 2013-03-22.

1.5 MW
Capacity
as recorded in REPD
Operational
Status
since 2013-03-22
Solar Photovoltaics
Technology
Anesco
West Berkshire
Authority
England

Planning and build timeline

Application submitted2012-09-14
Permission granted2012-12-14
3 months after submission
Operational2013-03-22
3 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

West Berkshire’s record on solar

West Berkshire has decided 22 solar farms and approved 95%, taking a median of 2.8 months. See every solar farm decision in West Berkshire

Other built sites within 15 km

SiteMWDistance
Limberlost Solar Farm
Battery · Operational
0.30 km
Gravel Works, Wasing Estate
Solar Photovoltaics · Operational
52.7 km
Berry Court Farm
Solar Photovoltaics · Operational
4.210.3 km
Berry Court Solar Farm - energy storage
Battery · Operational
110.5 km
Hill End Farm
Solar Photovoltaics · Operational
2.811.4 km
Minchens Lane Battery Storage Facility
Battery · Operational
10012.8 km
Pierces Farm
Solar Photovoltaics · Operational
1.714.8 km
Overton
Solar Photovoltaics · Operational
414.9 km

How big is Limberlost Farm?

Limberlost Farm has a recorded installed capacity of 1.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Limberlost Farm?

REPD records the operator as Anesco. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Limberlost Farm approved and built?

The application was submitted on 2012-09-14. Permission was granted on 2012-12-14, 3 months later. The site became operational on 2013-03-22, 3 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1272.