Limberlost Farm
Limberlost Farm is an operational 1.5 MW solar farm in West Berkshire, generating since 22 March 2013. Planning permission was granted on 14 December 2012, 3 months after submission. Operator of record: Anesco.
Planning and build timeline
| Application submitted | 14 September 2012 |
| Permission granted | 14 December 2012 3 months after submission |
| Operational | 22 March 2013 3 months after consent |
Screening a site of your own?
West Berkshire approves 95% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Limberlost Farm’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
West Berkshire’s record on solar
West Berkshire has decided 22 solar farms and approved 95%, taking a median of 2.8 months. See every solar farm decision in West Berkshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Battery · Operational | 0.3 | 0 km |
Solar Photovoltaics · Operational | 5 | 2.7 km |
Solar Photovoltaics · Operational | 4.2 | 10.3 km |
Battery · Operational | 1 | 10.5 km |
Solar Photovoltaics · Operational | 2.8 | 11.4 km |
Battery · Operational | 100 | 12.8 km |
Solar Photovoltaics · Operational | 1.7 | 14.8 km |
Solar Photovoltaics · Operational | 4 | 14.9 km |
How big is Limberlost Farm?
Limberlost Farm has a recorded installed capacity of 1.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Limberlost Farm?
REPD records the operator as Anesco. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Limberlost Farm approved and built?
The application was submitted on 14 September 2012. Permission was granted on 14 December 2012, 3 months later. The site became operational on 22 March 2013, 3 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1272.