Overton is an operational 4 MW solar farm in Basingstoke and Deane, generating since 15 December 2015. Planning permission was granted on 18 December 2014, 6 months after submission. Operator of record: British Solar Renewables.
Planning and build timeline
| Application submitted | 17 June 2014 |
| Permission granted | 18 December 2014 6 months after submission |
| Operational | 15 December 2015 12 months after consent |
Screening a site of your own?
Basingstoke and Deane approves 86% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Overton’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
- Nutrient-neutrality catchment — Solent: Includes Chichester and Langstone Harbours SPA/Ramsar, Solent and Southampton Water SPA/Ramsar, Solent Maritime SAC, Portsmouth Harbour SPA/Ramsar
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Basingstoke and Deane’s record on solar
Basingstoke and Deane has decided 21 solar farms and approved 86%, taking a median of 3.4 months. See every solar farm decision in Basingstoke and Deane →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 5 | 9.5 km |
Solar Photovoltaics · Operational | 5 | 10.1 km |
Anaerobic Digestion · Operational | 1.5 | 10.6 km |
Solar Photovoltaics · Operational | 2.8 | 13.3 km |
Battery · Operational | 1 | 14.2 km |
Solar Photovoltaics · Operational | 4.2 | 14.3 km |
Solar Photovoltaics · Operational | 40 | 14.3 km |
Solar Photovoltaics · Operational | 5 | 14.8 km |
How big is Overton?
Overton has a recorded installed capacity of 4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Overton?
REPD records the operator as British Solar Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Overton approved and built?
The application was submitted on 17 June 2014. Permission was granted on 18 December 2014, 6 months later. The site became operational on 15 December 2015, 12 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1848.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode