Renewable sites › Gravel Works, Wasing Estate
Gravel Works, Wasing Estate
Gravel Works, Wasing Estate is operational in West Berkshire with a recorded capacity of 5 MW, and has been generating since 2017-03-01.
Planning and build timeline
| Application submitted | 2015-03-20 |
| Permission granted | 2016-06-09 15 months after submission |
| Operational | 2017-03-01 9 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
West Berkshire’s record on solar
West Berkshire has decided 22 solar farms and approved 95%, taking a median of 2.8 months. See every solar farm decision in West Berkshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Limberlost Farm Solar Photovoltaics · Operational | 1.5 | 2.7 km |
Limberlost Solar Farm Battery · Operational | 0.3 | 2.7 km |
Berry Court Farm Solar Photovoltaics · Operational | 4.2 | 8.1 km |
Berry Court Solar Farm - energy storage Battery · Operational | 1 | 8.3 km |
Hill End Farm Solar Photovoltaics · Operational | 2.8 | 9.5 km |
Minchens Lane Battery Storage Facility Battery · Operational | 100 | 10.3 km |
Pierces Farm Solar Photovoltaics · Operational | 1.7 | 12.1 km |
Pingewood Road South Solar Photovoltaics · Operational | 15.8 | 13.1 km |
How big is Gravel Works, Wasing Estate?
Gravel Works, Wasing Estate has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Gravel Works, Wasing Estate?
REPD records the operator as NESF (formerly INRG Solar). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Gravel Works, Wasing Estate approved and built?
The application was submitted on 2015-03-20. Permission was granted on 2016-06-09, 15 months later. The site became operational on 2017-03-01, 9 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5143.