Renewable sitesGravel Works, Wasing Estate

Gravel Works, Wasing Estate

Gravel Works, Wasing Estate is an operational 5 MW solar farm in West Berkshire, generating since 1 March 2017. Planning permission was granted on 9 June 2016, 15 months after submission. Operator of record: NESF (formerly INRG Solar).

5 MW
Capacity
as recorded in REPD
Operational
Status
since 1 March 2017
Solar Photovoltaics
Technology
NESF (formerly INRG Solar)
West Berkshire
Authority
England

Planning and build timeline

Application submitted20 March 2015
Permission granted9 June 2016
15 months after submission
Operational1 March 2017
9 months after consent

Screening a site of your own?

RedlineUK · £39

West Berkshire approves 95% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Gravel Works, Wasing Estate’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

West Berkshire’s record on solar

West Berkshire has decided 22 solar farms and approved 95%, taking a median of 2.8 months. See every solar farm decision in West Berkshire

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
1.52.7 km
Battery · Operational
0.32.7 km
Solar Photovoltaics · Operational
4.28.1 km
Battery · Operational
18.3 km
Solar Photovoltaics · Operational
2.89.5 km
Battery · Operational
10010.3 km
Solar Photovoltaics · Operational
1.712.1 km
Solar Photovoltaics · Operational
15.813.1 km

How big is Gravel Works, Wasing Estate?

Gravel Works, Wasing Estate has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Gravel Works, Wasing Estate?

REPD records the operator as NESF (formerly INRG Solar). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Gravel Works, Wasing Estate approved and built?

The application was submitted on 20 March 2015. Permission was granted on 9 June 2016, 15 months later. The site became operational on 1 March 2017, 9 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5143.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode