Renewable sites › Land at Grange Farm
Land at Grange Farm
Land at Grange Farm is an operational 1.1 MW anaerobic digestion plant in West Lindsey, generating since 1 December 2014. Planning permission was granted on 4 June 2013, 3 months after submission. Operator of record: Lockwood Estates.
Planning and build timeline
| Application submitted | 25 February 2013 |
| Permission granted | 4 June 2013 3 months after submission |
| Operational | 1 December 2014 18 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in West Lindsey: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Land at Grange Farm’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Anaerobic Digestion · Under Construction | — | 8.3 km |
Battery · Operational | 10 | 8.7 km |
Solar Photovoltaics · Operational | 10.5 | 10.8 km |
Solar Photovoltaics · Operational | 3.3 | 10.8 km |
Solar Photovoltaics · Operational | 12 | 12.5 km |
Solar Photovoltaics · Operational | 22 | 12.5 km |
How big is Land at Grange Farm?
Land at Grange Farm has a recorded installed capacity of 1.1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Land at Grange Farm?
REPD records the operator as Lockwood Estates. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Land at Grange Farm approved and built?
The application was submitted on 25 February 2013. Permission was granted on 4 June 2013, 3 months later. The site became operational on 1 December 2014, 18 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 72.
Novarly Parcel · official public data, read properly · parcel.novarly.com