Renewable sites › Levenmouth demonstration turbine (Fife Energy Park)
Levenmouth demonstration turbine (Fife Energy Park)
Levenmouth demonstration turbine (Fife Energy Park) is operational in Scottish Government (S36) with a recorded capacity of 7 MW, and has been generating since 2014-03-31.
Planning and build timeline
| Application submitted | 2009-12-02 |
| Permission granted | 2011-11-18 24 months after submission |
| Operational | 2014-03-31 28 months after consent |
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Fife Energy Park - H100 Fife Hydrogen Demonstration Project Hydrogen · Under Construction | — | 4.3 km |
Banbeath Industrial Estate Solar Array Solar Photovoltaics · Under Construction | 4.19 | 6.1 km |
Diageo Biomass Energy Project Biomass (dedicated) · Operational | 5.5 | 6.9 km |
Earlseat Wind Onshore · Operational | 18.4 | 7.8 km |
Middle Balbeggie Solar Photovoltaics · Operational | 5 | 11.8 km |
West Strathore Solar Limited Solar Photovoltaics · Operational | 5 | 12 km |
Noble Foods Wind Onshore · Operational | 1.5 | 12.5 km |
Skeddoway Farm Wind Turbine Wind Onshore · Operational | 1.5 | 12.5 km |
How big is Levenmouth demonstration turbine (Fife Energy Park)?
Levenmouth demonstration turbine (Fife Energy Park) has a recorded installed capacity of 7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Levenmouth demonstration turbine (Fife Energy Park)?
REPD records the operator as Catapult. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Levenmouth demonstration turbine (Fife Energy Park) approved and built?
The application was submitted on 2009-12-02. Permission was granted on 2011-11-18, 24 months later. The site became operational on 2014-03-31, 28 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2528.
Novarly Parcel · official public data, read properly · parcel.novarly.com