Renewable sites › West Strathore Solar Limited
West Strathore Solar Limited
West Strathore Solar Limited is operational in Fife with a recorded capacity of 5 MW, and has been generating since 2017-03-30.
Planning and build timeline
| Application submitted | 2015-07-23 |
| Permission granted | 2015-11-26 4 months after submission |
| Operational | 2017-03-30 16 months after consent |
Fife’s record on solar
Fife has decided 31 solar farms and approved 100%, taking a median of 3.7 months. See every solar farm decision in Fife →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Noble Foods Wind Onshore · Operational | 1.5 | 0.5 km |
Skeddoway Farm Wind Turbine Wind Onshore · Operational | 1.5 | 0.6 km |
Middle Balbeggie Wind Turbines Wind Onshore · Operational | 6.4 | 1.5 km |
Middle Balbeggie Solar Photovoltaics · Operational | 5 | 1.9 km |
Inchdairnie Anaerobic Digestion · Operational | 2 | 4 km |
Markinch Biomass CHP Plant Biomass (dedicated) · Operational | 65 | 4.1 km |
Earlseat Wind Onshore · Operational | 18.4 | 4.4 km |
Kirkcaldy W W T W, Nether Street- Solar Panels Solar Photovoltaics · Operational | 0.65 | 5 km |
How big is West Strathore Solar Limited?
West Strathore Solar Limited has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates West Strathore Solar Limited?
REPD records the operator as West Strathore Solar. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was West Strathore Solar Limited approved and built?
The application was submitted on 2015-07-23. Permission was granted on 2015-11-26, 4 months later. The site became operational on 2017-03-30, 16 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5384.
Novarly Parcel · official public data, read properly · parcel.novarly.com