Fife Energy Park - H100 Fife Hydrogen Demonstration Project is under construction in Fife.

Capacity
as recorded in REPD
Under Construction
Status
no operational date
Hydrogen
Technology
Scottish Gas Networks
Fife
Authority
Scotland

Planning and build timeline

Application submitted2020-12-28
Permission granted2021-08-06
7 months after submission
Operationalnot recorded

Other built sites within 15 km

SiteMWDistance
Banbeath Industrial Estate Solar Array
Solar Photovoltaics · Under Construction
4.192.2 km
Diageo Biomass Energy Project
Biomass (dedicated) · Operational
5.52.6 km
Earlseat
Wind Onshore · Operational
18.44 km
Levenmouth demonstration turbine (Fife Energy Park)
Wind Offshore · Operational
74.3 km
West Strathore Solar Limited
Solar Photovoltaics · Operational
58.4 km
Middle Balbeggie
Solar Photovoltaics · Operational
58.7 km
Skeddoway Farm Wind Turbine
Wind Onshore · Operational
1.58.9 km
Noble Foods
Wind Onshore · Operational
1.58.9 km

How big is Fife Energy Park - H100 Fife Hydrogen Demonstration Project?

REPD does not record an installed capacity for Fife Energy Park - H100 Fife Hydrogen Demonstration Project.

Who operates Fife Energy Park - H100 Fife Hydrogen Demonstration Project?

REPD records the operator as Scottish Gas Networks. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Fife Energy Park - H100 Fife Hydrogen Demonstration Project approved and built?

The application was submitted on 2020-12-28. Permission was granted on 2021-08-06, 7 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 10243.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council