Renewable sites › Middle Balbeggie
Middle Balbeggie
Middle Balbeggie is an operational 5 MW solar farm in Fife, generating since 27 January 2017. Planning permission was granted on 17 December 2015, 3 months after submission. Operator of record: Lightsource Renewable Energy.
Planning and build timeline
| Application submitted | 16 September 2015 |
| Permission granted | 17 December 2015 3 months after submission |
| Operational | 27 January 2017 13 months after consent |
Screening a site of your own?
Fife approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Middle Balbeggie’s recorded coordinate — swap in your own postcode or coordinates.
Fife’s record on solar
Fife has decided 31 solar farms and approved 100%, taking a median of 3.7 months. See every solar farm decision in Fife →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 6.4 | 1.3 km |
Solar Photovoltaics · Operational | 5 | 1.9 km |
Wind Onshore · Operational | 1.5 | 2 km |
Wind Onshore · Operational | 1.5 | 2.2 km |
Solar Photovoltaics · Operational | 0.65 | 3.2 km |
Wind Onshore · Operational | 18.4 | 5 km |
Anaerobic Digestion · Operational | 2 | 5.3 km |
Biomass (dedicated) · Operational | 65 | 6 km |
How big is Middle Balbeggie?
Middle Balbeggie has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Middle Balbeggie?
REPD records the operator as Lightsource Renewable Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Middle Balbeggie approved and built?
The application was submitted on 16 September 2015. Permission was granted on 17 December 2015, 3 months later. The site became operational on 27 January 2017, 13 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5797.