Renewable sitesLeeming Bar (Waste AD)

Leeming Bar (Waste AD)

Leeming Bar (Waste AD) is operational in North Yorkshire with a recorded capacity of 1.5 MW, and has been generating since 2016-01-15.

1.5 MW
Capacity
as recorded in REPD
Operational
Status
since 2016-01-15
Anaerobic Digestion
Technology
JFS Biogas
North Yorkshire
Authority
England

Planning and build timeline

Application submitted2013-07-30
Permission granted2015-04-02
20 months after submission
Operational2016-01-15
9 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Non Agricultural agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Vale Of Mowbray Limited - Solar Photovoltaic System
Solar Photovoltaics · Under Construction
12 km
North East of Ainderby Steeple
Solar Photovoltaics · Operational
5.95.1 km
Heck Food, Lime Lane - Solar Panels
Solar Photovoltaics · Operational
0.248.6 km
Land East of Appleton Farm
Solar Photovoltaics · Operational
59.6 km
Land North of Sandhutton Lane
Solar Photovoltaics · Operational
511.2 km
Scorton
Landfill Gas · Operational
112.8 km
Barugh Farm
Solar Photovoltaics · Operational
513.3 km

How big is Leeming Bar (Waste AD)?

Leeming Bar (Waste AD) has a recorded installed capacity of 1.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Leeming Bar (Waste AD)?

REPD records the operator as JFS Biogas. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Leeming Bar (Waste AD) approved and built?

The application was submitted on 2013-07-30. Permission was granted on 2015-04-02, 20 months later. The site became operational on 2016-01-15, 9 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 330.