Renewable sitesLand North of Sandhutton Lane

Land North of Sandhutton Lane

Land North of Sandhutton Lane is an operational 5 MW solar farm in North Yorkshire, generating since 15 February 2017. Planning permission was granted on 25 September 2015, 4 months after submission. Operator of record: Greencoat Capital.

5 MW
Capacity
as recorded in REPD
Operational
Status
since 15 February 2017
Solar Photovoltaics
Technology
Greencoat Capital
North Yorkshire
Authority
England

Planning and build timeline

Application submitted25 May 2015
Permission granted25 September 2015
4 months after submission
Operational15 February 2017
17 months after consent

Screening a site of your own?

RedlineUK · £39

North Yorkshire approves 96% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Land North of Sandhutton Lane’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

North Yorkshire’s record on solar

North Yorkshire has decided 105 solar farms and approved 96%, taking a median of 2.7 months. See every solar farm decision in North Yorkshire

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
0.246 km
Solar Photovoltaics · Operational
59.2 km
Solar Photovoltaics · Operational
59.4 km
Anaerobic Digestion · Operational
1.511.2 km
Solar Photovoltaics · Operational
5.911.3 km
Solar Photovoltaics · Under Construction
113 km
Solar Photovoltaics · Operational
514.7 km

How big is Land North of Sandhutton Lane?

Land North of Sandhutton Lane has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Land North of Sandhutton Lane?

REPD records the operator as Greencoat Capital. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Land North of Sandhutton Lane approved and built?

The application was submitted on 25 May 2015. Permission was granted on 25 September 2015, 4 months later. The site became operational on 15 February 2017, 17 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5297.