Renewable sitesHeck Food, Lime Lane - Solar Panels

Heck Food, Lime Lane - Solar Panels

Heck Food, Lime Lane - Solar Panels is operational in North Yorkshire with a recorded capacity of 0.24 MW, and has been generating since 2024-06-07.

0.24 MW
Capacity
as recorded in REPD
Operational
Status
since 2024-06-07
Solar Photovoltaics
Technology
Duncan Renewables
North Yorkshire
Authority
England

Planning and build timeline

Application submitted2023-10-18
Permission granted2023-12-08
2 months after submission
Operational2024-06-07
6 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

North Yorkshire’s record on solar

North Yorkshire has decided 105 solar farms and approved 96%, taking a median of 2.7 months. See every solar farm decision in North Yorkshire

Other built sites within 15 km

SiteMWDistance
Barugh Farm
Solar Photovoltaics · Operational
55.2 km
Land North of Sandhutton Lane
Solar Photovoltaics · Operational
56 km
Leeming Bar (Waste AD)
Anaerobic Digestion · Operational
1.58.6 km
Vale Of Mowbray Limited - Solar Photovoltaic System
Solar Photovoltaics · Under Construction
110.6 km
North East of Ainderby Steeple
Solar Photovoltaics · Operational
5.911.4 km
Cold Harbour Farm
Solar Photovoltaics · Operational
512.5 km

How big is Heck Food, Lime Lane - Solar Panels?

Heck Food, Lime Lane - Solar Panels has a recorded installed capacity of 0.24 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Heck Food, Lime Lane - Solar Panels?

REPD records the operator as Duncan Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Heck Food, Lime Lane - Solar Panels approved and built?

The application was submitted on 2023-10-18. Permission was granted on 2023-12-08, 2 months later. The site became operational on 2024-06-07, 6 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 15091.