Land off Moss Side Lane is an operational 5 MW solar farm in Fylde, generating since 31 March 2017. Planning permission was granted on 17 November 2015, 3 months after submission. Operator of record: WEL Solar Park 11.

5 MW
Capacity
as recorded in REPD
Operational
Status
since 31 March 2017
Solar Photovoltaics
Technology
WEL Solar Park 11
Fylde
Authority
England

Planning and build timeline

Application submitted6 August 2015
Permission granted17 November 2015
3 months after submission
Operational31 March 2017
16 months after consent

Screening a site of your own?

RedlineUK · £39

Fylde approves 86% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Land off Moss Side Lane’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Fylde’s record on solar

Fylde has decided 14 solar farms and approved 86%, taking a median of 4.3 months. See every solar farm decision in Fylde

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
4.92.1 km
Anaerobic Digestion · Operational
12.9 km
Solar Photovoltaics · Operational
53.7 km
Solar Photovoltaics · Under Construction
0.75.3 km
Solar Photovoltaics · Operational
4.55.8 km
Solar Photovoltaics · Operational
3.27 km
Battery · Operational
27.2 km
Solar Photovoltaics · Operational
1.37.4 km

How big is Land off Moss Side Lane?

Land off Moss Side Lane has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Land off Moss Side Lane?

REPD records the operator as WEL Solar Park 11. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Land off Moss Side Lane approved and built?

The application was submitted on 6 August 2015. Permission was granted on 17 November 2015, 3 months later. The site became operational on 31 March 2017, 16 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5928.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode