Cooper House Farm

Cooper House Farm is an operational 5 MW solar farm in Fylde, generating since 15 March 2016. Planning permission was granted on 6 November 2015, 6 months after submission. Operator of record: Suncredit UK/ Vogt solar.

5 MW
Capacity
as recorded in REPD
Operational
Status
since 15 March 2016
Solar Photovoltaics
Technology
Suncredit UK/ Vogt solar
Fylde
Authority
England

Planning and build timeline

Application submitted13 May 2015
Permission granted6 November 2015
6 months after submission
Operational15 March 2016
4 months after consent

Screening a site of your own?

RedlineUK · £39

Fylde approves 86% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Cooper House Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Fylde’s record on solar

Fylde has decided 14 solar farms and approved 86%, taking a median of 4.3 months. See every solar farm decision in Fylde

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
3.23.5 km
Battery · Operational
23.6 km
Solar Photovoltaics · Operational
53.7 km
Solar Photovoltaics · Operational
1.33.7 km
Anaerobic Digestion · Operational
14 km
Solar Photovoltaics · Operational
54.4 km
Solar Photovoltaics · Operational
1.74.6 km
Landfill Gas · Operational
3.35 km

How big is Cooper House Farm?

Cooper House Farm has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Cooper House Farm?

REPD records the operator as Suncredit UK/ Vogt solar. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Cooper House Farm approved and built?

The application was submitted on 13 May 2015. Permission was granted on 6 November 2015, 6 months later. The site became operational on 15 March 2016, 4 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5321.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode