Cooper House Farm is operational in Fylde with a recorded capacity of 5 MW, and has been generating since 2016-03-15.

5 MW
Capacity
as recorded in REPD
Operational
Status
since 2016-03-15
Solar Photovoltaics
Technology
Suncredit UK/ Vogt solar
Fylde
Authority
England

Planning and build timeline

Application submitted2015-05-13
Permission granted2015-11-06
6 months after submission
Operational2016-03-15
4 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Fylde’s record on solar

Fylde has decided 14 solar farms and approved 86%, taking a median of 4.3 months. See every solar farm decision in Fylde

Other built sites within 15 km

SiteMWDistance
Clifton Marsh Wastewater Treatment Works
Solar Photovoltaics · Operational
3.23.5 km
Clifton Marsh Waste Water Treatment Works
Battery · Operational
23.6 km
Land off Moss Side Lane
Solar Photovoltaics · Operational
53.7 km
Clifton Marsh Wastewater Treatment Works
Solar Photovoltaics · Operational
1.33.7 km
Carr Farm (Farm AD)
Anaerobic Digestion · Operational
14 km
Oakfield Farm
Solar Photovoltaics · Operational
54.4 km
Oakfield Farm - extension
Solar Photovoltaics · Operational
1.74.6 km
Clifton Marsh Energy
Landfill Gas · Operational
3.35 km

How big is Cooper House Farm?

Cooper House Farm has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Cooper House Farm?

REPD records the operator as Suncredit UK/ Vogt solar. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Cooper House Farm approved and built?

The application was submitted on 2015-05-13. Permission was granted on 2015-11-06, 6 months later. The site became operational on 2016-03-15, 4 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5321.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council