Solar planning in Fylde

Fylde has decided 14 solar farms and approved 86% of them, taking a median of 4.3 months to decide. Consented capacity: 58 MW. 3 applications still awaiting a decision.

86%
Approved
12 granted · 2 refused
4.3 mo
Median decision
UK 2.3 mo
58 MW
Consented
10 MW refused
0
Appeals
no appeals recorded

How Fylde compares

Against the 298 UK authorities with 5+ solar decisions, Fylde sits in the 17th percentile for approval rate (7 points below the England average) and the 13th percentile for speed.

Decisions by year

510Approved — 6 (2015)Refused — 1 (2015)715Refused — 1 (2017)117Approved — 2 (2018)218Approved — 2 (2023)223Approved — 1 (2024)124Approved — 1 (2025)125
Approved Refused

Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (19)

SchemeMWStatusDecided
Merlewood Caravan Park, Cartford Lane - Solar Panels
MW Estates Limited · 25/0230
0.15Application Withdrawn2025-11-24
National Car Parks, St Georges Road - Solar Panels
Conway Group · 25/0340 · 1.7 mo to decide
Awaiting Construction2025-07-25
Peel Road Phase 2 - Solar Farm
Energi Generation · 25/0113
13Application Submitted2025-02-28
Weeton Barracks, Grantham Road - Solar Panels
Defence Infrastructure Organisation · 24/0184 · 4.4 mo to decide
0.7Under Construction2024-09-06
Clifton Marsh Farm, Preston New Road - Solar Farm
Vattenfall · 24/0414
49.9Application Submitted2024-07-22
Three Nooks Wood, Weeton Road - Solar Panels
RG & JM Towers · 22/0915 · 1.4 mo to decide
1.3Awaiting Construction2023-03-15
Lawns Solar Farm
Lightsource Limited · 21/0904 · 15.4 mo to decide
25Awaiting Construction2023-02-01
Clifton Marsh Wastewater Treatment Works
United Utilities Water/ Preston City Council · LCC/2017/0090 · 9 mo to decide
3.2Operational2018-08-23
Clifton Marsh Wastewater Treatment Works
United Utilities · LCC/2017/0074 · 9.6 mo to decide
1.3Operational2018-05-23
Clifton Marsh Wwtw
United Utilities · LCC/2016/0007 · 12 mo to decide
4.5Application Refused2017-01-20
Newfold Solar Farm
New Energy for the World · 15/0501 · 3.6 mo to decide
5Abandoned2015-12-15
Oakfield Farm - extension
Renewable Source · 15/0679 · 2.4 mo to decide
1.7Operational2015-12-14
Land To The South Of Todderstaffe
Solar Power Inc UK Services/SPI China (HK) · 15/0380 · 5 mo to decide
4.5Operational2015-11-17
Land off Moss Side Lane
WEL Solar Park 11 · 15/0530 · 3.4 mo to decide
5Operational2015-11-17
Cooper House Farm
Suncredit UK/ Vogt solar · 15/0329 · 5.8 mo to decide
5Operational2015-11-06
Cask Farm
Lightsource Renewable Energy · 15/0406 · 3.8 mo to decide
5Application Refused2015-10-12
Staining Wood Farm
Lightsource Renewable Energy · 15/0337 · 4.4 mo to decide
4.9Operational2015-09-30
Oakfield Farm
Renewable Source · 14/0811 · 2.3 mo to decide
5Operational2015-04-01
Land off Moss Side Lane
Solar Park Developments · 14/0696 · 4.1 mo to decide
18Revised2015-02-04

Does Fylde approve solar farms?

Yes — of the 14 solar farms Fylde has decided, 86% were approved (12 granted, 2 refused). The UK-wide rate for solar is 93%.

How long does a solar farm application take in Fylde?

The median time from application to decision is 4.3 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much solar capacity has Fylde consented?

58 MW has been consented across 12 approved schemes, with 10 MW refused. A further 3 applications awaits a decision.

Other technologies in Fylde

Battery storage in FyldeOnshore wind in Fylde

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.